Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 886 MW
Manager NEM Real Time Operations
INC0138597 - RESOLVED - EMMS
SERVICE INTERRUPTION - SERVICE RESTORED
The Electricity Market Management System service has been restored.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
INC0138597 - ALERT - EMMS
AEMO is experiencing a service interruption relating to the Electricity Market Management System service.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Inter-Regional Transfer limit variation - Murraylink
Inter-Regional Transfer limit variation - Murraylink
There has been an unplanned outage of Murraylink.
The following constraint set was invoked at 1405 hrs 25/11/2024
I-ML_ZERO
The constraint set contains the following interconnector on the left hand side.
V-S-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Request for Generator Recall Information for the period 27/11/2024 for Region QLD
Refer to AEMO Electricity Market Notice no. 120895.
Please provide Generator Recall Information for the period from 27/11/2024, by 1500 hrs on 25/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
Request for Generator Recall Information for the period 27/11/2024 for Region NSW
Refer to AEMO Electricity Market Notice no. 120894, and 120892.
Please provide Generator Recall Information for the period from 27/11/2024, by 1500 hrs on 25/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
Cancellation of Actual (LOR1) condition in the NSW region - 24/11/2024
Cancellation of Actual (LOR1) condition in the NSW region - 24/11/2024
The Actual LOR1 Condition in the NSW region advised in AEMO Electricity Market Notice No.120889 is cancelled at 1845 hrs 24/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 24/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 24/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1541 MW
The minimum capacity reserve available is 1460 MW
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024
Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024
At 1911 hrs 22/11/2024 there was an unplanned outage of the No.2 leg of Directlink.
The following constraint set(s) invoked at 1920 hrs 22/11/2024
N-X_MBTE_2
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations