Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 120912
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2330 hrs 26/11/2024.
The foreseeable circumstance requiring the need for intervention is Voltage
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 26/11/2024, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2330 hrs 26/11/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
[EventId:202411231900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 23 November 2024 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 23 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 November 2024.
Refer to market notice: 120871
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 23 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411231840_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 23 November 2024 18:40
Issued by Australian Energy Market Operator Ltd at 1840 hrs on 23 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1840 hrs on 23 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202411231815_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 23 November 2024 18:15
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 23 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 November 2024.
Refer to market notice: 120869
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1815 hrs on 23 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411231800_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 23 November 2024 18:00
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 23 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1800 hrs on 23 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202411221940_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 November 2024 19:40
Issued by Australian Energy Market Operator Ltd at 1940 hrs on 22 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 November 2024.
Refer to market notice: 120834
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1940 hrs on 22 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411221820_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 November 2024 18:20
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 22 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1820 hrs on 22 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202411221230_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 November 2024 12:30
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 22 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 November 2024.
Refer to market notice: 120787
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1230 hrs on 22 November 2024.
This is an AEMO autogenerated Market Notice.