120753RESERVE NOTICE21/11/2024 03:48:37 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120718 has been updated at 1400 hrs 21/11/2024 to the following:

1. From 1130 hrs to 1400 hrs 26/11/2024.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 680 MW.

2. From 1900 hrs to 2030 hrs 26/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 788 MW.


AEMO Operations
     
120752RESERVE NOTICE21/11/2024 03:51:41 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

From 1730 hrs to 1830 hrs 24/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1273 MW.


AEMO Operations

     
120751RESERVE NOTICE21/11/2024 03:47:11 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120717 has been updated at 1400 hrs 21/11/2024 to the following:

1. From 1400 hrs to 1600 hrs 25/11/2024.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 680 MW.

2. From 1900 hrs to 2030 hrs 25/11/2024.
The forecast capacity reserve requirement is 1460 MW.
The minimum capacity reserve available is 730 MW.



AEMO Operations
     
120749RESERVE NOTICE21/11/2024 01:55:16 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120739 has been updated at 1300 hrs 21/11/2024 to the following:

From 1400 hrs to 1900 hrs 26/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 171 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
120747MARKET INTERVENTION21/11/2024 01:42:14 PM

Cancellation - AEMO Intervention Event - SA region 15/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 15/11/2024

Refer to Market Notice 120499

The AEMO Intervention Event and all associated directions are cancelled from 1335 hrs on 21/11/2024.


Manager NEM Real Time Operations
     
120746RESERVE NOTICE21/11/2024 01:57:49 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 26/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120741 is cancelled at 1300 hrs 21/11/2024.


AEMO Operations
     
120745MARKET INTERVENTION21/11/2024 01:35:59 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 120723

Direction is cancelled from: 1330 hrs 21/11/2024

Manager NEM Real Time Operations
     
120744MARKET INTERVENTION21/11/2024 01:30:24 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 120722

Direction is cancelled from: 1330 hrs 21/11/2024

Manager NEM Real Time Operations
     
120741RESERVE NOTICE21/11/2024 01:17:32 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1800 hrs to 1830 hrs 26/11/2024.
The forecast capacity reserve requirement is 736 MW.
The minimum capacity reserve available is 647 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm