Market Notices

119811MINIMUM SYSTEM LOAD02/11/2024 06:02:13 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 03/11/2024

AEMO ELECTRICITY MARKET NOTICE
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 03/11/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1770 MW
o MSL2 - 1270 MW
o MSL3 - 770 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:

From 1100 hrs to 1400 hrs 03/11/2024. Minimum regional demand is forecast to be 1424 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

Manager NEM Real Time Operations
     
119774MINIMUM SYSTEM LOAD02/11/2024 12:11:56 PM

Cancellation - Forecast Minimum System Load MSL1 condition in the VIC Region on 02/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Forecast Minimum System Load MSL1 condition in the VIC Region at 1200 hrs 02/11/2024.

Refer to Market Notice 119742.

Manager NEM Real Time Operations
     
119760MINIMUM SYSTEM LOAD03/11/2024 11:49:58 AM

Actual Minimum System Load MSL1 condition in the VIC Region on 03/11/2024

AEMO ELECTRICITY MARKET NOTICE
Actual Minimum System Load MSL1 condition in the VIC Region on 03/11/2024

Update to Market Notice 119811 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 03/11/2024.

Minimum regional demand is forecast to be 1623 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1770 MW
- MSL2 - 1270 MW
- MSL3 - 770 MW

The regional demand is below the MSL1 threshold. The actual MSL1 condition is forecast to exist until 1400 hrs.

Manager NEM Real Time Operations
     
119743MINIMUM SYSTEM LOAD01/11/2024 04:14:34 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 05/11/2024

AEMO ELECTRICITY MARKET NOTICE
Update to Market Notice 119682 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 05/11/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1535 MW
o MSL2 - 1035 MW
o MSL3 - 535 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:

From 1000 hrs to 1430 hrs 05/11/2024. Minimum regional demand is forecast to be 1106 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO Operations
     
119742MINIMUM SYSTEM LOAD01/11/2024 04:13:32 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 02/11/2024

AEMO ELECTRICITY MARKET NOTICE
Update to Market Notice 119644 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 02/11/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1685 MW
o MSL2 - 1185 MW
o MSL3 - 685 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:

From 1030 hrs to 1400 hrs 02/11/2024. Minimum regional demand is forecast to be 1304 MW at 1230 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO Operations
     
119741MINIMUM SYSTEM LOAD01/11/2024 04:10:05 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 03/11/2024

AEMO ELECTRICITY MARKET NOTICE
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 03/11/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1795 MW
o MSL2 - 1295 MW
o MSL3 - 795 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:

From 1130 hrs to 1330 hrs 03/11/2024. Minimum regional demand is forecast to be 1684 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO Operations
     
119701NON-CONFORMANCE31/10/2024 02:01:14 PM

NON-CONFORMANCE Region NSW1 Thursday, 31 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE Region NSW1 Thursday, 31 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:.

Unit: MP1
Duration: 31/10/2024 13:25 to 31/10/2024 13:30
Amount: -52 MW
Constraint: NC-N_MP1

Manager NEM Real Time Operations
     
119699NON-CONFORMANCE31/10/2024 01:05:15 PM

NON-CONFORMANCE Region QLD1 Thursday, 31 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 31 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 31/10/2024 12:50 to 31/10/2024 13:05
Amount: 24 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
119691POWER SYSTEM EVENTS31/10/2024 03:45:23 AM

Update - Non-credible contingency event - NSW region - 31/10/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 31/10/2024

Refer AEMO Electricity Market Notice 119689

At 0345 hrs the Wagga B 330 kV bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     