Market Notices

113487SETTLEMENTS RESIDUE19/01/2024 04:00:29 PM

[EventId:202401191600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 19 January 2024 16:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1600 hrs on 19 January 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 January 2024.

Refer to market notice: 113478

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 19 January 2024.

This is an AEMO autogenerated Market Notice.
113478SETTLEMENTS RESIDUE19/01/2024 02:35:18 PM

[EventId:202401191435_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 19 January 2024 14:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1435 hrs on 19 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1435 hrs on 19 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
113462SETTLEMENTS RESIDUE18/01/2024 09:25:23 PM

[EventId:202401182125_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 18 January 2024 21:25

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2125 hrs on 18 January 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 18 January 2024.

Refer to market notice: 113459

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 2125 hrs on 18 January 2024.

This is an AEMO autogenerated Market Notice.
113460SETTLEMENTS RESIDUE18/01/2024 08:50:23 PM

[EventId:202401182050_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 18 January 2024 20:50

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2050 hrs on 18 January 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 18 January 2024.

Refer to market notice: 113449

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2050 hrs on 18 January 2024.

This is an AEMO autogenerated Market Notice.
113459SETTLEMENTS RESIDUE18/01/2024 08:35:30 PM

[EventId:202401182035_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 18 January 2024 20:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2035 hrs on 18 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 18 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 2035 hrs on 18 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
113456SETTLEMENTS RESIDUE18/01/2024 07:50:22 PM

[EventId:202401181950_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 18 January 2024 19:50

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1950 hrs on 18 January 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 18 January 2024.

Refer to market notice: 113442

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1950 hrs on 18 January 2024.

This is an AEMO autogenerated Market Notice.
113449SETTLEMENTS RESIDUE18/01/2024 07:36:38 PM

[EventId:202401181935_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 18 January 2024 19:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1935 hrs on 18 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 18 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1935 hrs on 18 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
113442SETTLEMENTS RESIDUE18/01/2024 07:00:18 PM

[EventId:202401181900_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 18 January 2024 19:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 18 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 18 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1900 hrs on 18 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
113441SETTLEMENTS RESIDUE18/01/2024 06:50:20 PM

[EventId:202401181850_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 18 January 2024 18:50

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1850 hrs on 18 January 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 18 January 2024.

Refer to market notice: 113438

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1850 hrs on 18 January 2024.

This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm