112188INTER-REGIONAL TRANSFER11/12/2023 04:31:45 PM

Inter-regional transfer limit variation - Blyth West- Munno Para 275 kV Line - SA region - 11/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Blyth West- Munno Para 275 kV Line - SA region - 11/12/2023

At 1446 hrs 11/12/2023 there was an unplanned outage of Blyth West- Munno Para 275 kV Line.

However, due to the concurrent Non-credible contingency event - SA region - 11/12/2023, refer AEMO Electricity Market Notice 112187, additional inter-regional constraints were not required until the remaining Mintaro - Waterloo 132 kV Line was returned to service.

The following constraint set(s) invoked at 1610 hrs 11/12/2023
S-BWMP

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112184RESERVE NOTICE11/12/2023 03:14:50 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112179 is cancelled at 1400 hrs 11/12/2023.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
112179RESERVE NOTICE11/12/2023 01:37:21 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1630 hrs 14/12/2023 to 1800 hrs 14/12/2023.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 655 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
112129RESERVE NOTICE09/12/2023 09:45:57 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112125 is cancelled at 0945 hrs 09/12/2023.

Manager NEM Real Time Operations
112125RESERVE NOTICE09/12/2023 05:19:58 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112119 has been updated at 0515 hrs 09/12/2023 to the following:

From 1700 hrs 09/12/2023 to 1800 hrs 09/12/2023.
The forecast capacity reserve requirement is 704 MW.
The minimum capacity reserve available is 625 MW.

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1130 hrs on 09/12/2023.

Manager NEM Real Time Operations
112119RESERVE NOTICE08/12/2023 05:27:17 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112081 has been updated at 1715 hrs 08/12/2023 to the following:

From 1600 hrs 09/12/2023 to 1800 hrs 09/12/2023.
The forecast capacity reserve requirement is 987 MW.
The minimum capacity reserve available is 761 MW.

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1130 hrs on 09/12/2023.

Manager NEM Real Time Operations
112081RESERVE NOTICE08/12/2023 01:21:12 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1600 hrs 09/12/2023 to 1830 hrs 09/12/2023.
The forecast capacity reserve requirement is 1180 MW.
The minimum capacity reserve available is 766 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
112076RESERVE NOTICE08/12/2023 11:52:29 AM

STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112041 has been updated at 1100 hrs 08/12/2023 to the following:

From 1530 hrs 09/12/2023 to 1830 hrs 09/12/2023.
The forecast capacity reserve requirement is 1250 MW.
The minimum capacity reserve available is 776 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
112050INTER-REGIONAL TRANSFER08/12/2023 01:18:51 AM

Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

Refer AEMO Electricity Market Notice 112048

AEMO has been notified that the controls to vary Murraylink output are now available.

Constraint set I-CTRL_ISSUE_ML revoked at 0115 hrs.

Manager NEM Real Time Operations