112137RESERVE NOTICE09/12/2023 05:16:02 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/12/2023

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.

The Actual LOR1 condition is forecast to exist until 1830 hrs.

The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1344 MW.

Manager NEM Real Time Operations
112118NON-CONFORMANCE08/12/2023 05:10:37 PM

NON-CONFORMANCE Region QLD1 Friday, 8 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 8 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SWAN_E
Duration: 08/12/2023 17:05 to 08/12/2023 17:10
Amount: 20 MW
Constraint: NC-Q_SWAN_E

Auto-generated on behalf of Manager NEM Real Time Operations
112080NON-CONFORMANCE08/12/2023 12:50:18 PM

NON-CONFORMANCE Region NSW1 Friday, 8 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 8 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SUNTPSF1
Duration: 08/12/2023 12:35 to 08/12/2023 12:50
Amount: 76 MW
Constraint: NC-N_SUNTPSF1

Auto-generated on behalf of Manager NEM Real Time Operations
112058MARKET SYSTEMS08/12/2023 07:05:32 AM

CHG0082118 | Completed | Production | Planned System Maintenance activity.

Change Number: CHG0082118
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Network Outage Scheduler
Change Title: Planned System Maintenance activity.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
112023MARKET SYSTEMS06/12/2023 10:40:07 AM

CHG0082190 | Completed | Pre-Production | Pre-Prod MSATS Mertering Exemption Release #2

Change Number: CHG0082190
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS Mertering Exemption Release #2
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
112022NON-CONFORMANCE06/12/2023 08:45:17 AM

NON-CONFORMANCE Region NSW1 Wednesday, 6 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 6 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SUNTPSF1
Duration: 06/12/2023 07:30 to 06/12/2023 08:45
Amount: 51 MW
Constraint: NC-N_SUNTPSF1

Auto-generated on behalf of Manager NEM Real Time Operations
112017RESERVE NOTICE05/12/2023 06:48:43 PM

Cancellation of Actual (LOR1) condition in the NSW region - 05/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 05/12/2023

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112016 is cancelled at 1845 hrs 05/12/2023.

Manager NEM Real Time Operations
112016RESERVE NOTICE05/12/2023 06:21:33 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/12/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/12/2023

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1350 MW

Manager NEM Real Time Operations
112009NON-CONFORMANCE05/12/2023 12:45:20 PM

NON-CONFORMANCE Region NSW1 Tuesday, 5 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 5 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: NEWENSF1
Duration: 05/12/2023 12:25 to 05/12/2023 12:45
Amount: 25 MW
Constraint: NC-N_NEWENSF1

Auto-generated on behalf of Manager NEM Real Time Operations