PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 22/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1830 hrs 22/01/2024 to 1900 hrs 22/01/2024.
The forecast capacity reserve requirement is 599 MW.
The minimum capacity reserve available is 533 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
OR
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 22/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113550 is cancelled at 1520 hrs 21/01/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 22/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1830 hrs 22/01/2024 to 1930 hrs 22/01/2024.
The forecast capacity reserve requirement is 604 MW.
The minimum capacity reserve available is 515 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 21/01/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 113526 is cancelled at 1445 hrs 20/01/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 21/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1830 hrs 21/01/2024 to 1900 hrs 21/01/2024.
The forecast capacity reserve requirement is 1293 MW.
The minimum capacity reserve available is 1248 MW.
AEMO is seeking a market response.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 22/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113466 is cancelled at 1000 hrs 19/01/2024.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 22/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113465 has been updated at 0900 hrs 19/01/2024 to the following:
From 1830 hrs to 1900 hrs 22/01/2024.
The forecast capacity reserve requirement is 714 MW.
The minimum capacity reserve available is 563 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 22/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1900 hrs 22/01/2024.
The forecast capacity reserve requirement is 720 MW.
The minimum capacity reserve available is 708 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
CHG0082626 | Completed | Production | EMMS Production - FTP/Participant Intrface - Preventative maintenance.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Expedited
Service/Component: EMMS - Dispatch
Change Title: EMMS Production - FTP/Participant Intrface - Preventative maintenance.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.