Market Notices

119315MINIMUM SYSTEM LOAD24/10/2024 02:52:43 PM

Forecast Minimum System Load 1 (MSL1) in the VIC Region on 27/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 27/10/2024.

Minimum regional demand is forecast to be 1648 MW at 1300 hrs, and the advisory threshold is:
MSL1 - 1860 MW
MSL2 - 1360 MW
MSL3 - 860 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1400 hrs 27/10/2024.

AEMO Operations
     
119236MINIMUM SYSTEM LOAD23/10/2024 03:03:39 PM

Forecast Minimum System Load 1 (MSL1) in the VIC Region on 26/10/2024

AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 119194 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 26/10/2024.

Minimum regional demand is forecast to be 1465 MW at 1300 hrs, and the advisory threshold is:
MSL1 - 1685 MW
MSL2 - 1185 MW
MSL3 - 685 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1400 hrs 26/10/2024.

AEMO Operations
     
119202INTER-REGIONAL TRANSFER23/10/2024 06:42:52 AM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 23/10/2024

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_SYDS_562A9792 from 0635 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

V-S-MNSP1
V-SA
VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     
119194MINIMUM SYSTEM LOAD22/10/2024 03:13:38 PM

Forecast Minimum System Load 1 (MSL1) in the VIC Region on 26/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 26/10/2024.

Minimum regional demand is forecast to be 1645 MW at 1300 hrs, and the advisory threshold is:
MSL1 - 1685 MW
MSL2 - 1185 MW
MSL3 - 685 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1230 hrs to 1300 hrs 26/10/2024.

AEMO Operations
     
119056INTER-REGIONAL TRANSFER19/10/2024 01:10:23 PM

Inter-regional transfer limit variation - Tamworth No 1 330 kV bus and Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/10/2024

AEMO ELECTRICITY MARKET NOTICE

Tamworth No 1 330 kV bus and Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/10/2024

A planned outage of Tamworth No 1 330 kV bus in the NSW region was scheduled from 1100 hrs 18/10/2024 to 1700 hrs 20/10/2024.
A planned outage of Tamworth - Armidale No. 86 330 kV Line in the NSW region was scheduled from 0500 hrs 09/10/2024 to 1700 hrs 20/10/2024.

The outage has been completed by 1250 hrs 19/10/2024.

Constraint set(s) invoked:
N-ARTW_86
N-LDTW_84
N-TW_SVC
N-TW_330_BUS1

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1


Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
119027GENERAL NOTICE18/10/2024 08:01:30 PM

Network Augmentation Commissioned - NSW Region - 18/10/2024

AEMO ELECTRICITY MARKET NOTICE

A network augmentation has been commissioned in the NSW region at 2000 hrs 18/10/2024 as follows:

Stubo 330kV switching station has been cut into the existing Wellington - Wollar West 79 330 kV line to form the following circuits:

Wellington - Stubo SF 79 330 kV Transmission Line
Wollar West - Stubo SF 7M 330 kV Transmission Line

Manager NEM Real Time Operations
     
118998INTER-REGIONAL TRANSFER17/10/2024 07:20:04 PM

Inter-regional transfer limit variation - Brinkworth- Red Hill- Bungama 132kV lines - SA region - 17/10/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Brinkworth- Red Hill- Bungama 132kV lines - SA region - 17/10/2024

At 1846 hrs 17/10/2024 there was an unplanned outage of Brinkworth- Red Hill- Bungama 132kV lines.

The following constraint set(s) invoked at 1855 hrs 17/10/2024
S-BRBG

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
118997INTER-REGIONAL TRANSFER17/10/2024 07:18:47 PM

Inter-regional transfer limit variation - Hummocks - Bungama 132kV line - SA region - 17/10/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Bungama 132kV line - SA region - 17/10/2024

At 1842 hrs 17/10/2024 there was an unplanned outage of Hummocks - Bungama 132kV line.

The following constraint set(s) invoked at 1850 hrs 17/10/2024
S-HUBG

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
118996INTER-REGIONAL TRANSFER17/10/2024 07:13:32 PM

Inter-regional transfer limit variation - Blyth West - Munno Para 275kV line- SA region - 17/10/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Blyth West - Munno Para 275kV line - SA region - 17/10/2024

At 1848 hrs 17/10/2024 there was an unplanned outage of Blyth West - Munno Para 275kV line.

The following constraint set(s) invoked at 1855 hrs 17/10/2024
S-BWMP

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm