Filter by category
Filter by Date
Cancellation - MSL1- VIC Region at 1315 hrs 26/10/2024.
Cancellation - MSL1- VIC Region at 1315 hrs 26/10/2024.
Refer to Market Notice 119423 for MSL1.
Manager NEM Real Time Operations
Forecast Minimum System Load 1 (MSL1) in the VIC Region on 26/10/2024
Update to Market Notice 119236 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 26/10/2024.
Minimum regional demand is forecast to be 1302 MW at 1230 hrs, and the advisory threshold is:
MSL1 - 1685 MW
MSL2 - 1185 MW
MSL3 - 685 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1000 hrs to 1400 hrs 26/10/2024.
AEMO Operations
Forecast Minimum System Load 1 (MSL1) in the VIC Region on 27/10/2024
Update to Market Notice 119315 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 27/10/2024.
Minimum regional demand is forecast to be 1732 MW at 1230 hrs, and the advisory threshold is:
MSL1 = 1795 MW
MSL2 = 1295 MW
MSL3 = 795 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1330 hrs 26/10/2024.
AEMO Operations
Forecast Minimum System Load 1 (MSL1) in the VIC Region on 27/10/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 27/10/2024.
Minimum regional demand is forecast to be 1648 MW at 1300 hrs, and the advisory threshold is:
MSL1 - 1860 MW
MSL2 - 1360 MW
MSL3 - 860 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1400 hrs 27/10/2024.
AEMO Operations
Forecast Minimum System Load 1 (MSL1) in the VIC Region on 26/10/2024
Update to Market Notice 119194 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 26/10/2024.
Minimum regional demand is forecast to be 1465 MW at 1300 hrs, and the advisory threshold is:
MSL1 - 1685 MW
MSL2 - 1185 MW
MSL3 - 685 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1400 hrs 26/10/2024.
AEMO Operations
Forecast Minimum System Load 1 (MSL1) in the VIC Region on 26/10/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 26/10/2024.
Minimum regional demand is forecast to be 1645 MW at 1300 hrs, and the advisory threshold is:
MSL1 - 1685 MW
MSL2 - 1185 MW
MSL3 - 685 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1230 hrs to 1300 hrs 26/10/2024.
AEMO Operations
Non-credible contingency event - VIC region - 18/10/2024
Non-credible contingency event - VIC region - 18/10/2024
At 1525 hrs the Rowville - Yallourn No. 7 220 kV Line and the Rowville - Yallourn No. 8 220 kV Line tripped and auto-reclosed.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 18/10/2024
A network augmentation has been commissioned in the NSW region at 2000 hrs 18/10/2024 as follows:
Stubo 330kV switching station has been cut into the existing Wellington - Wollar West 79 330 kV line to form the following circuits:
Wellington - Stubo SF 79 330 kV Transmission Line
Wollar West - Stubo SF 7M 330 kV Transmission Line
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 17/10/2024
Cancellation of Actual (LOR1) condition in the QLD region - 17/10/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.118993 is cancelled at 1839 hrs 17/10/2024.
Manager NEM Real Time Operations