Cancellation of Actual (LOR1) condition in the NSW region - 09/05/2024
Cancellation of Actual (LOR1) condition in the NSW region - 09/05/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.116566 is cancelled at 1915 hrs 09/05/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/05/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs.
The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 964 MW
Manager NEM Real Time Operations
[EventId:198] AP STARTED for ENERGY in NSW1 at 09 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 09 May 2024
ADMINISTERED PRICE PERIOD DECLARED in NSW1 region.
AEMO has determined that the rolling sum of the uncapped spot prices for the NSW1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,490,200.00.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 0405 hrs on 09 May 2024 and will continue through to the end of that trading day.
An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the NSW1 region.
An administered floor price (AFP) of -600 $/MWh will apply to spot prices.
AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.
This is an AEMO autogenerated Market Notice.
[EventId:197] AP ENDED for ENERGY in NSW1 at 09 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 08 May 2024
ADMINISTERED PRICE PERIOD ENDS in NSW1 region.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO is notifying market participants that the administered price period declared for the NSW1 region in market notice 116550 will end at 0400 hrs on 09 May 2024.
This is an AEMO autogenerated Market Notice.
[EventId:197] AP STARTED for ENERGY in NSW1 at 08 May 2024 19:45
Issued by Australian Energy Market Operator Ltd at 1945 hrs on 08 May 2024
ADMINISTERED PRICE PERIOD DECLARED in NSW1 region.
AEMO has determined that the rolling sum of the uncapped spot prices for the NSW1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,490,200.00.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 1955 hrs on 08 May 2024 and will continue through to the end of that trading day.
An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the NSW1 region.
An administered floor price (AFP) of -600 $/MWh will apply to spot prices.
AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.
This is an AEMO autogenerated Market Notice.
Cancellation of Actual (LOR1) condition in the NSW region - 08/05/2024
Cancellation of Actual (LOR1) condition in the NSW region - 08/05/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.116547 is cancelled at 1915 hrs 08/05/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/05/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs.
The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 1417 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 07/05/2024
Cancellation of Actual (LOR1) condition in the NSW region - 07/05/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No. 116513 is cancelled at 1915 hrs 07/05/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/05/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 1366 MW
Manager NEM Real Time Operations