Market Notices

118421MINIMUM SYSTEM LOAD24/09/2024 02:54:54 PM

Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs to 1400 hrs 28/09/2024.
Minimum regional demand is forecast to be 1638 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

AEMO Operations
     
115196RECALL GEN CAPACITY27/02/2024 08:27:52 AM

Request for Generator Recall Information for 29/02/2024 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 115193. Additional generation in QLD could assist in alleviating the forecast LOR2 condition in NSW.

Please provide Generator Recall Information for the period 29/02/2024, by 1200 hrs 28/02/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
115195RECALL GEN CAPACITY27/02/2024 08:26:49 AM

Request for Generator Recall Information for 29/02/2024 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 115193.

Please provide Generator Recall Information for the period 29/02/2024, by 1200 hrs 28/02/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
113958RESERVE NOTICE29/01/2024 09:17:19 AM

STPASA - Suspect Lack Of Reserve Level 3 (LOR3) in the QLD Region on 01/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO considers that there are suspect Forecast LOR3 conditions for the QLD region for the following periods:

1. From 0900 hrs to 1000 hrs 01/02/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 38 MW at 0930 hrs.

2. From 1130 hrs to 1200 hrs 01/02/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 62 MW at 1130 hrs.

AEMO is currently investigating these LOR3 forecast conditions to confirm whether they are valid.

AEMO Operations
112201RECALL GEN CAPACITY12/12/2023 10:59:40 AM

Request for Generator Recall Information for 14/12/2023 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 112198. Additional generation in QLD could assist in alleviating the forecast LOR condition in NSW.

Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
112200RECALL GEN CAPACITY12/12/2023 11:01:01 AM

Request for Generator Recall Information for 14/12/2023 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 112198.

Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf