Filter by category
Filter by Date
Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024
Update to Market Notice 118421.
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1030 hrs to 1430 hrs 28/09/2024.
Minimum regional demand is forecast to be 1420 MW at 1200 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW
MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.
Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem
AEMO is seeking a market response.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.
AEMO Operations
Minimum System Load 1 (MSL1) in the VIC Region on 27/09/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1300 hrs 27/09/2024 to 1330 hrs 27/09/2024.
Minimum regional demand is forecast to be 1879 MW at 1330 hrs, and the advisory threshold is:
o MSL1 - 1915 MW
o MSL2 - 1415 MW
o MSL3 - 915 MW
MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.
Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem
AEMO is seeking a market response.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.
AEMO Operations
Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs to 1400 hrs 28/09/2024.
Minimum regional demand is forecast to be 1638 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW
MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.
Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem
AEMO is seeking a market response.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.
AEMO Operations
Cancellation of Actual (LOR2) condition in the VIC region - 13/02/2024
Cancellation of Actual (LOR2) condition in the VIC region - 13/02/2024
The Actual LOR2 Condition in the VIC Region advised in AEMO Electricity Market Notice No.114589 is cancelled at 1614 hrs 13/02/2024.
Manager NEM Real Time Operations
STPASA - Suspect Lack Of Reserve Level 3 (LOR3) in the QLD Region on 01/02/2024
AEMO considers that there are suspect Forecast LOR3 conditions for the QLD region for the following periods:
1. From 0900 hrs to 1000 hrs 01/02/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 38 MW at 0930 hrs.
2. From 1130 hrs to 1200 hrs 01/02/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 62 MW at 1130 hrs.
AEMO is currently investigating these LOR3 forecast conditions to confirm whether they are valid.
AEMO Operations
Cancellation of Actual (LOR2) condition in the NSW region - 14/12/2023
Cancellation of Actual (LOR2) condition in the NSW region - 14/12/2023
The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112362 is cancelled at 1810 hrs 14/12/2023.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 14/12/2023
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 14/12/2023
An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR2 condition is not forecast in Pre Dispatch
The capacity reserve required is 690 MW
The minimum reserve available is 678 MW
AEMO is seeking an immediate market response.
An insufficient market response may require AEMO to implement a AEMO intervention event.
Manager NEM Real Time Operations