Filter by category
Filter by Date
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121992 has been updated at 1144 hrs to the following:
[1.] From 1730 hrs 16/12/2024 to 1800 hrs 16/12/2024.
The forecast capacity reserve requirement is 1340 MW.
The minimum capacity reserve available is 1277 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121999 has been updated at 1100 hrs 16/12/2024 to the following:
From 1500 hrs to 1900 hrs 17/12/2024.
The forecast capacity reserve requirement is 1130 MW.
The minimum capacity reserve available is 444 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121995 has been updated at 1000 hrs 16/12/2024 to the following:
From 1500 hrs to 1930 hrs 17/12/2024.
The forecast capacity reserve requirement is 1164 MW.
The minimum capacity reserve available is 133 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121960 has been updated at 0800 hrs 16/12/2024 to the following:
From 1500 hrs to 1900 hrs 17/12/2024.
The forecast capacity reserve requirement is 1012 MW.
The minimum capacity reserve available is 408 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
NON-CONFORMANCE Region QLD1 Monday, 16 December 2024
NON-CONFORMANCE QLD1 Region Monday, 16 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 16/12/2024 02:20 to 16/12/2024 03:30
Amount: -18 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 16 December 2024
NON-CONFORMANCE QLD1 Region Monday, 16 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 16/12/2024 01:10 to 16/12/2024 01:50
Amount: -21 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121949 has been updated at
1900 hrs to the following:
[1.] From 1700 hrs 16/12/2024 to 1800 hrs 16/12/2024.
The forecast capacity reserve requirement is 1350 MW.
The minimum capacity reserve available is 1143 MW.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 17/12/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121899 has been updated at 1430 hrs 15/12/2024 to the following:
[1.] From 1400 hrs 17/12/2024 to 1430 hrs 17/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1307 MW.
[2.] From 2130 hrs 17/12/2024 to 2230 hrs 17/12/2024.
The forecast capacity reserve requirement is 1859 MW.
The minimum capacity reserve available is 1203 MW.
AEMO Operations