Market Notices

118323CONSTRAINTS19/09/2024 04:20:22 PM

Update to system normal constraint equation in NSW for transient voltage stability in south-west NSW

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 92840.

Transgrid has advised AEMO of an update to the transient voltage stability limit in south-west NSW for loss of Darlington Point to Wagga (63) 330 kV line. The limit will include terms for the Darlington Point and Riverina BESS.

The following constraint equation will be updated with the above changes at 1100 hrs Friday 20th September 2024.
N::N_NIL_63

For full details on the formulation, the new constraint equation has now been loaded into AEMO's pre-production systems.

For further details on these constraint equation please contact ben.blake@aemo.com.au

Ben Blake
AEMO Operations
118322POWER SYSTEM EVENTS19/09/2024 04:16:27 PM

Update - Non-credible contingency event - TAS region - 19/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 19/09/2024

Refer AEMO Electricity Market Notice 118321

At 1446 hrs the Gordon - Chapel St No 1 and No 2 220 kV lines were returned to service.

This non-credible contingency event was caused by lightning. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.


Manager NEM Real Time Operations
118321POWER SYSTEM EVENTS19/09/2024 03:28:41 PM

Update - Non-credible contingency event - TAS region - 19/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 19/09/2024

At 1340 hrs the Gordon - Chapel St No1 and No 2 220 kV lines tripped.

AEMO did not instruct load shedding.

AEMO has advised of approximately 112 MW disconnection of bulk electrical load,
disconnection of generation at Studland Bay Wind generator (71 MW) and 23 MW generation reduction at Gordon Power station.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
118320POWER SYSTEM EVENTS19/09/2024 01:54:59 PM

Non-credible contingency event - TAS region - 19/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 19/09/2024

At 1340 hrs the Gordon - Chapel St No1 and No 2 220 kV lines tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
118171POWER SYSTEM EVENTS06/09/2024 08:18:58 PM

Update - Non-credible contingency event - VIC region - 06/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - VIC region - 06/09/2024

Refer AEMO Electricity Market Notice 118166

At 2005 hrs the Loy Yang PS No. 4 500 kV bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
118170PRICE ADJUSTMENT06/09/2024 07:20:01 PM

Prices for intervals on 05/09/2024 from 13:55 to 15:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Refer AEMO Electricity Market Notice 118149 and 118150.

PRICES ARE NOW REVISED to Market Suspension Pricing Schedule for trading intervals on 05/09/2024 from 1355 hrs to 1510 hrs.

Manager Electricity Market Monitoring
118166POWER SYSTEM EVENTS06/09/2024 12:38:00 PM

Non-credible contingency event - VIC region - 06/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 06/09/2024

At 1222 hrs the Loy Yang PS No. 4 500 kV bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
117909POWER SYSTEM EVENTS28/08/2024 02:17:12 AM

Update - Non-credible contingency event - VIC region - 28/08/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - VIC region - 28/08/2024

Refer AEMO Electricity Market Notice 117908

At 0134 hrs the APD No 2 Potline was returned to service.

At 0200 hrs the APD No 1 Potline was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
117908POWER SYSTEM EVENTS28/08/2024 01:02:22 AM

Non-credible contingency event - VIC region - 28/08/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 28/08/2024

At 0001 hrs the APD No1 Potline and the APD No 2 Potline tripped.

AEMO did not instruct load shedding.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm