Filter by category
Filter by Date
NON-CONFORMANCE Region NSW1 Saturday, 2 December 2023
NON-CONFORMANCE NSW1 Region Saturday, 2 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 02/12/2023 11:40 to 02/12/2023 11:50
Amount: -16 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA, VIC from 01 Dec 2023 to 05 Dec 2023
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 4th Dec
VIC
Mildura Ap (39+ Deg C): 5th Dec
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
CHG0082190 | Pre-Production | Pre-Prod MSATS Mertering Exemption Release #2
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS Mertering Exemption Release #2
Change Start Date & Time: 05/12/2023 12:00:00 AEST
Change End Date & Time: 06/12/2023 12:00:00 AEST
Outage Start Date & Time: 05/12/2023 12:00:00 AEST
Outage End Date & Time: 05/12/2023 16:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .