PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 19/10/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
From 1800 hrs 19/10/2024 to 1930 hrs 19/10/2024.
The forecast capacity reserve requirement is 1081 MW.
The minimum capacity reserve available is 906 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 18/10/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1730 hrs 18/10/2024 to 1830 hrs 18/10/2024.
The forecast capacity reserve requirement is 1190 MW.
The minimum capacity reserve available is 1091 MW.
Manager NEM Real Time Operations
[EventId:202410171130_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 17 October 2024 11:30
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 17 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 17 October 2024.
Refer to market notice: 118966
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1130 hrs on 17 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410171035_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 17 October 2024 10:35
Issued by Australian Energy Market Operator Ltd at 1035 hrs on 17 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 17 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1035 hrs on 17 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410161500_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 16 October 2024 15:00
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 16 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 October 2024.
Refer to market notice: 118931
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1500 hrs on 16 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410161335_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 16 October 2024 13:35
Issued by Australian Energy Market Operator Ltd at 1335 hrs on 16 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1335 hrs on 16 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410151900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 October 2024 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 15 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 October 2024.
Refer to market notice: 118917
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 15 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410151735_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 October 2024 17:35
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 15 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1735 hrs on 15 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/10/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 118878 is cancelled at 1400 hrs 15/10/2024
AEMO Operations