Filter by category
Filter by Date
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 02/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116433 is cancelled at 1500 hrs 02/05/2024.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 09/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
From 0000 hrs to 0200 hrs 09/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1304 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 08/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
From 0500 hrs to 0830 hrs 08/05/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1265 MW.
From 1530 hrs to 2359 hrs 08/05/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1252 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 07/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
From 1700 hrs to 1800 hrs 07/05/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1355 MW.
AEMO Operations.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 02/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1700 hrs 02/05/2024 to 1830 hrs 02/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1390 MW.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 29 April 2024
NON-CONFORMANCE NSW1 Region Monday, 29 April 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 29/04/2024 20:50 to 29/04/2024 20:55
Amount: -18 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Monday, 29 April 2024
NON-CONFORMANCE VIC1 Region Monday, 29 April 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: JLB01
Duration: 29/04/2024 13:00 to 29/04/2024 13:05
Amount: 35 MW
Constraint: NC-V_JLB01
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Friday, 26 April 2024
NON-CONFORMANCE VIC1 Region Friday, 26 April 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS3
Duration: 26/04/2024 22:40 to 26/04/2024 22:45
Amount: 17 MW
Constraint: NC-V_YWPS3
Auto-generated on behalf of Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 26/04/2024
Non-credible contingency event - NSW region - 26/04/2024
At 1112 hrs the Griffith to Darlington Point 132kV line (99K) and the Darlington Point BESS disconnected.
AEMO did not instruct load shedding.
AEMO observed 5 MW of electrical load lost.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations