Market Notices

112003INTER-REGIONAL TRANSFER04/12/2023 04:44:47 PM

Inter-Regional Transfer limit variation - Murraylink power transfer limit reduction due to high temperature.

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink power transfer limit reduction due to high temperature.

Murraylink power transfer limit has been reduced based on APA advice, consistent with the high ambient temperatures in the vicinity of Murraylink (Berri and Redcliffe).

Constraint sets I-SVML_165 and I-VSML_165 invoked from 1640 hrs.

The constraint set contains equations with the following interconnector on the LHS:

V-S-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
111986NON-CONFORMANCE04/12/2023 09:25:19 AM

NON-CONFORMANCE Region QLD1 Monday, 4 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 4 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: STAN-1
Duration: 04/12/2023 09:20 to 04/12/2023 09:25
Amount: -31 MW
Constraint: NC-Q_STAN-1

Auto-generated on behalf of Manager NEM Real Time Operations
111971INTER-REGIONAL TRANSFER03/12/2023 04:38:17 PM

Inter-regional transfer limit variation - H2 South Pine 275kV SVC - QLD region - 03/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - H2 South Pine 275kV SVC - QLD region - 03/12/2023

At 1626 hrs 03/12/2023 there was an unplanned outage of H2 South Pine 275kV SVC.

The following constraint set(s) invoked at 1630 hrs 03/12/2023
Q-SP_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1 - QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
111918NON-CONFORMANCE02/12/2023 11:50:11 AM

NON-CONFORMANCE Region NSW1 Saturday, 2 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 2 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 02/12/2023 11:40 to 02/12/2023 11:50
Amount: -16 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
111896MARKET SYSTEMS01/12/2023 09:48:04 AM

CHG0082190 | Pre-Production | Pre-Prod MSATS Mertering Exemption Release #2

Change Number: CHG0082190
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS Mertering Exemption Release #2
Change Start Date & Time: 05/12/2023 12:00:00 AEST
Change End Date & Time: 06/12/2023 12:00:00 AEST
Outage Start Date & Time: 05/12/2023 12:00:00 AEST
Outage End Date & Time: 05/12/2023 16:00:00 AEST

Environment: Pre-Production

Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm