Filter by category
Filter by Date
Inter-regional transfer limit variation - Para No.1 and No.2 275 kV SVC - SA region - 29/12/2023
Inter-regional transfer limit variation -Para No.1 and No.2 275 kV SVC - SA region - 29/12/2023
At 0355 hrs 29/12/2023 there was a short notice outage of Para No.1 and No.2 275 kV SVC.
The following constraint set(s) invoked at 0355 hrs 29/12/2023
S-X_PA_VC_2
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Para No.1 275 kV SVC - SA region - 29/12/2023
Inter-regional transfer limit variation -Para No.1 275 kV SV - SA region - 29/12/2023
At 0145 hrs 29/12/2023 there was a short notice outage of Para No.1 275 kV SVC.
The following constraint set(s) invoked at 0145 hrs 29/12/2023
S-PA_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Blyth West - Munno Para 275 kV line - SA region - 28/12/2023
Inter-regional transfer limit variation - Blyth West - Munno Para 275 kV line - SA region - 28/12/2023
At 2115 hrs 28/12/2023 there was an unplanned outage of the Blyth West - Munno Para 275 kV line.
The following constraint set(s) invoked at 2125 hrs 28/12/2023
S-BWMP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 28/12/2023
Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 28/12/2023
At 1913 hrs 28/12/2023 there was an unplanned outage of the Hummocks - Waterloo 132 kV line.
The following constraint set(s) invoked at 1925 hrs 28/12/2023
S-HUWT
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 28/12/2023
Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 28/12/2023
Refer AEMO Electricity Market Notice 112852.
Constraint set CA_SYDS_549FBEF5 revoked 1850 hrs.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 28/12/2023
Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 28/12/2023
In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYDS_549FBEF5 from 1830 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
[EventId:202312271400_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 December 2023 14:00
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 27 December 2023
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 December 2023.
Refer to market notice: 112810
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1400 hrs on 27 December 2023.
This is an AEMO autogenerated Market Notice.
[EventId:202312271245_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 27 December 2023 12:45
Issued by Australian Energy Market Operator Ltd at 1245 hrs on 27 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1245 hrs on 27 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Pelican Point Circuit Breaker 8093 - SA region - 26/12/2023
Inter-regional transfer limit variation - Pelican Point Circuit Breaker 8093 - SA region - 26/12/2023
At 1832 hrs 26/12/2023 there was a short notice outage of Pelican Point Circuit Breaker 8093.
The following constraint set(s) invoked at 1855 hrs 26/12/2023
S-PPT_CB6727
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations