Filter by category
Filter by Date
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116926 is cancelled at 1400 hrs 12/06/2024.
AEMO Operations
CHG0089854: Short Term Trading Market
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 12/06/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 116933 for the 12/06/2024 is cancelled at 1445 hrs 11/06/2024.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 0000 hrs to 0030 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1759 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
1. From 0630 hrs to 0830 hrs 18/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1612 MW.
2. From 1600 hrs to 2359 hrs 18/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1455 MW.
AEMO Operations
NON-CONFORMANCE Region QLD1 Tuesday, 11 June 2024
NON-CONFORMANCE QLD1 Region Tuesday, 11 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 11/06/2024 12:45 to 11/06/2024 14:25
Amount: -23 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 12/06/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 0830 hrs 12/06/2024 to 0900 hrs 12/06/2024.
The forecast capacity reserve requirement is 421 MW.
The minimum capacity reserve available is 393 MW.
[2.] From 0930 hrs 12/06/2024 to 1000 hrs 12/06/2024.
The forecast capacity reserve requirement is 419 MW.
The minimum capacity reserve available is 407 MW.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 11 June 2024
NON-CONFORMANCE QLD1 Region Tuesday, 11 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 11/06/2024 11:15 to 11/06/2024 12:05
Amount: -21 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0089972 | Completed | Production | Planned Maintenance to Norwest Internet firewall.
Notification issued to: Market Notice Notification
Type: Completed
Change Type: Normal Service/Component: Internet Access
Change Title: Planned Maintenance to Norwest Internet firewall.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.