Cancellation of Actual (LOR1) condition in the QLD region - 19/01/2024
Cancellation of Actual (LOR1) condition in the QLD region - 19/01/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113498 is cancelled at 2000 hrs 19/01/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 19/01/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 19/01/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch
The capacity reserve requirement is 982 MW
The minimum capacity reserve available is 938 MW
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 22/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113466 is cancelled at 1000 hrs 19/01/2024.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 22/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113465 has been updated at 0900 hrs 19/01/2024 to the following:
From 1830 hrs to 1900 hrs 22/01/2024.
The forecast capacity reserve requirement is 714 MW.
The minimum capacity reserve available is 563 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 22/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1900 hrs 22/01/2024.
The forecast capacity reserve requirement is 720 MW.
The minimum capacity reserve available is 708 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
NON-CONFORMANCE Region NSW1 Friday, 19 January 2024
NON-CONFORMANCE NSW1 Region Friday, 19 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MP2
Duration: 19/01/2024 07:00 to 19/01/2024 07:05
Amount: 16 MW
Constraint: NC-N_MP2
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 18/01/2024
Cancellation of Actual (LOR1) condition in the QLD region - 18/01/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113424 is cancelled at 1815 hrs 18/01/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 18/01/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 18/01/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1530 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs
The capacity reserve requirement is 952 MW
The minimum capacity reserve available is 857 MW
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 18 January 2024
NON-CONFORMANCE NSW1 Region Thursday, 18 January 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: DPNTBG1, DPNTBL1
Aggregate Dispatch Group: DPNTBESS_ADG1
Duration: 18/01/2024 14:50 to 18/01/2024 15:20
Amount: 19 MW
Constraint: NC-N_DPNTBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations