Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 24/09/2024
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 24/09/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2300 hrs.
The Actual LOR1 condition is forecast to exist until 0200 hrs
The capacity reserve requirement is 600 MW
The minimum capacity reserve available is 520 MW
Manager NEM Real Time Operations
Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs to 1400 hrs 28/09/2024.
Minimum regional demand is forecast to be 1638 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW
MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.
Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem
AEMO is seeking a market response.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.
AEMO Operations
Update to system normal constraint equation in NSW for transient voltage stability in south-west NSW
Refer to market notice 92840.
Transgrid has advised AEMO of an update to the transient voltage stability limit in south-west NSW for loss of Darlington Point to Wagga (63) 330 kV line. The limit will include terms for the Darlington Point and Riverina BESS.
The following constraint equation will be updated with the above changes at 1100 hrs Friday 20th September 2024.
N::N_NIL_63
For full details on the formulation, the new constraint equation has now been loaded into AEMO's pre-production systems.
For further details on these constraint equation please contact ben.blake@aemo.com.au
Ben Blake
AEMO Operations
Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024
Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.118298 is cancelled at 1915 hrs 16/09/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1274 MW
Manager NEM Real Time Operations
Prices for intervals on 05/09/2024 from 13:55 to 15:10 are now confirmed
Refer AEMO Electricity Market Notice 118149 and 118150.
PRICES ARE NOW REVISED to Market Suspension Pricing Schedule for trading intervals on 05/09/2024 from 1355 hrs to 1510 hrs.
Manager Electricity Market Monitoring
Cancellation of Actual (LOR1) condition in the SA region - 05/08/2024
Cancellation of Actual (LOR1) condition in the SA region - 05/08/2024
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No. 117564 is cancelled at 2145 hrs 05/08/2024.
Manager NEM Real Time Operations
Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024
Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024
The actual LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117563 has been updated at 2120 hrs to the following:
The Actual LOR1 condition is forecast to exist until 2130 hrs.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 377 MW.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2030 hrs.
The Actual LOR1 condition is forecast to exist until 2100 hrs.
The capacity reserve requirement is 450 MW
The minimum capacity reserve available is 428 MW
Manager NEM Real Time Operations