[EventId:202412180915_review] Prices for interval 18-Dec-2024 09:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 0910 hrs on 18 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Dec-2024 09:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412180910_review] Prices for interval 18-Dec-2024 09:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 0905 hrs on 18 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Dec-2024 09:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412180905_review] Prices for interval 18-Dec-2024 09:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 0900 hrs on 18 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Dec-2024 09:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the NSW Region on 17/12/2024
The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122113 is cancelled at 1745 hrs 17/12/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 17/12/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 17/12/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1530 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs
The capacity reserve requirement is 1340 MW
The minimum capacity reserve available is 1082 MW
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 122013
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 19/12/2024.
The direction update is issued at 1630 hrs 17/12/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 122012
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 19/12/2024.
The direction update is issued at 1630 hrs 17/12/2024.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122093 is cancelled at 1140 hrs 17/12/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122070 has been updated to the following:
[1.] From 1600 hrs 17/12/2024 to 1800 hrs 17/12/2024.
The forecast capacity reserve requirement is 745 MW.
The minimum capacity reserve available is 611 MW.
AEMO estimates the latest time at which it would need to intervene through an AEMO intervention event is 1400 hrs on 17/12/2024.
Manager NEM Real Time Operations