[EventId:202411221130_confirmed] Prices for interval 22-Nov-2024 11:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1145 hrs on 22 November 2024
PRICES ARE NOW CONFIRMED for trading interval 22-Nov-2024 11:30.
In accordance with Market Notice 120799 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411221120_confirmed] Prices for interval 22-Nov-2024 11:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1145 hrs on 22 November 2024
PRICES ARE NOW CONFIRMED for trading interval 22-Nov-2024 11:20.
In accordance with Market Notice 120796 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 27/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120791 has been updated at 1000 hrs 22/11/2024 to the following:
From 1630 hrs to 1930 hrs 27/11/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 516 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120790 is cancelled at 1000 hrs 22/11/2024.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 27/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
1. From 1400 hrs to 1500 hrs 27/11/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 445 MW.
2. From 1600 hrs to 2000 hrs 27/11/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 72 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1730 hrs to 1900 hrs 27/11/2024.
The forecast capacity reserve requirement is 525 MW.
The minimum capacity reserve available is 263 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120740 is cancelled at 0900 hrs 22/11/2024.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 24/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120775 is cancelled at 0800 hrs 22/11/2024.
AEMO Operations
[EventId:202411220835_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 November 2024 08:35
Issued by Australian Energy Market Operator Ltd at 0835 hrs on 22 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0835 hrs on 22 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.