Market Notices

123528MARKET INTERVENTION21/01/2025 04:07:18 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123504

TORRB3 TORRENS ISLAN at 0800 hrs 21/01/2025 to Remain synchronised and follow dispatch targets.

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 23/01/2025.

The direction update is issued at 1605 hrs 21/01/2025.

Manager NEM Real Time Operations
     
123527MARKET INTERVENTION21/01/2025 03:58:37 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123505

Direction is cancelled from: 1630 hrs 21/01/2025

Manager NEM Real Time Operations
     
123526SETTLEMENTS RESIDUE21/01/2025 02:50:21 PM

[EventId:202501211450_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 21 January 2025 14:50

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1450 hrs on 21 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1450 hrs on 21 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123525RESERVE NOTICE21/01/2025 02:53:07 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 123471 is cancelled at 1400 hrs 21/01/2025.

AEMO Operations
     
123523RESERVE NOTICE21/01/2025 02:54:08 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1630 hrs to 1700 hrs 28/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1073 MW.

AEMO Operations
     
123519SETTLEMENTS RESIDUE21/01/2025 01:31:23 PM

[EventId:202501211330_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 21 January 2025 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 21 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 January 2025.

Refer to market notice: 123515

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1330 hrs on 21 January 2025.

This is an AEMO autogenerated Market Notice.
     
123517GENERAL NOTICE21/01/2025 01:23:56 PM

Network Augmentation Commissioned - NSW Region - 21/01/2025

AEMO ELECTRICITY MARKET NOTICE

Refer Market notice: 123507

Network Augmentation Commissioned - NSW Region - 21/01/2025

Commissioned: Bundey to Buronga 330 kV (6F) line.
Buronga No. 5 330 kV/330 kV phase shifting transformer

Manager NEM Real Time Operations
     
123516GENERAL NOTICE21/01/2025 12:13:17 PM

Update - Pre dispatch demand forecast error - NEM regions

AEMO ELECTRICITY MARKET NOTICE

Update - Pre dispatch demand forecast error - NEM regions

Refer market notice: 123513

The issue relating to the Pre dispatch demand forecast error has been resolved.

Manager NEM Real Time Operations
     
123515SETTLEMENTS RESIDUE21/01/2025 11:35:34 AM

[EventId:202501211135_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 21 January 2025 11:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1135 hrs on 21 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1135 hrs on 21 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     