PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
[1.] From 1700 hrs 08/05/2024 to 1900 hrs 08/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1125 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 09/05/2024 to 1800 hrs 09/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1351 MW.
Manager NEM Real Time Operations
[EventId:202405080830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 May 2024 08:30
Issued by Australian Energy Market Operator Ltd at 0830 hrs on 8 May 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 May 2024.
Refer to market notice: 116521
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 0830 hrs on 8 May 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202405080635_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 May 2024 06:35
Issued by Australian Energy Market Operator Ltd at 0635 hrs on 8 May 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 May 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0635 hrs on 8 May 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 08/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116519 is cancelled at 0615 hrs 08/05/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 0700 hrs 08/05/2024 to 0730 hrs 08/05/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1357 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 08/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116506 is cancelled at 2015 hrs 07/05/2024.
Manager NEM Real Time Operations
[EventId:202405071930_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 07 May 2024 19:30
Issued by Australian Energy Market Operator Ltd at 1930 hrs on 7 May 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 May 2024.
Refer to market notice: 116512
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1930 hrs on 7 May 2024.
This is an AEMO autogenerated Market Notice.
Cancellation of Actual (LOR1) condition in the NSW region - 07/05/2024
Cancellation of Actual (LOR1) condition in the NSW region - 07/05/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No. 116513 is cancelled at 1915 hrs 07/05/2024.