Filter by category
Filter by Date
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 30/07/2024
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117468 has been updated at 1400 hrs 27/07/2024 to the following:
From 0730 hrs 30/07/2024 to 0930 hrs 30/07/2024.
The forecast capacity reserve requirement is 557 MW.
The minimum capacity reserve available is 501 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 29/07/2024
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117467 has been updated at 1400 hrs 27/07/2024 to the following:
[1.] From 0700 hrs 29/07/2024 to 0930 hrs 29/07/2024.
The forecast capacity reserve requirement is 557 MW.
The minimum capacity reserve available is 470 MW.
[2.] From 1730 hrs 29/07/2024 to 1930 hrs 29/07/2024.
The forecast capacity reserve requirement is 557 MW.
The minimum capacity reserve available is 534 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 30/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:
From 0730 hrs to 0900 hrs 30/07/2024.
The forecast capacity reserve requirement is 555 MW.
The minimum capacity reserve available is 537 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 29/07/2024
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117442 has been updated at 1400 hrs 26/07/2024 to the following:
From 0700 hrs to 0930 hrs 29/07/2024.
The forecast capacity reserve requirement is 555 MW.
The minimum capacity reserve available is 461 MW.
AEMO Operations
Network Augmentation Commissioned - VIC Region - 30/07/2024
Network Augmentation Commissioned - VIC Region - 30/07/2024
Cressy Terminal Station has been cut into the existing Moorabool - Mortlake No.2 500 kV line to form the following circuits:
Cressy - Mortlake No.2 500 kV line
Cressy - Moorabool No.2 500 kV line
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 31/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:
From 0800 hrs to 0900 hrs 31/07/2024.
The forecast capacity reserve requirement is 555 MW.
The minimum capacity reserve available is 524 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 29/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:
From 0730 hrs to 0900 hrs 29/07/2024.
The forecast capacity reserve requirement is 555 MW.
The minimum capacity reserve available is 524 MW.
AEMO Operations
[EventId:202407251115_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 25 July 2024 11:15
Issued by Australian Energy Market Operator Ltd at 1115 hrs on 25 July 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 25 July 2024.
Refer to market notice: 117439
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.
The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1115 hrs on 25 July 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202407251000_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 25 July 2024 10:00
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 25 July 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 25 July 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.
The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1000 hrs on 25 July 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.