Filter by category
Filter by Date
[EventId:202312081550_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 December 2023 15:50
Issued by Australian Energy Market Operator Ltd at 1550 hrs on 8 December 2023
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 December 2023.
Refer to market notice: 112094
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1550 hrs on 8 December 2023.
This is an AEMO autogenerated Market Notice.
[EventId:202312081450_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 December 2023 14:50
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 8 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1450 hrs on 8 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region NSW1 Friday, 8 December 2023
NON-CONFORMANCE NSW1 Region Friday, 8 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: SUNTPSF1
Duration: 08/12/2023 12:35 to 08/12/2023 12:50
Amount: 76 MW
Constraint: NC-N_SUNTPSF1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202312081120_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 December 2023 11:20
Issued by Australian Energy Market Operator Ltd at 1120 hrs on 8 December 2023
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 December 2023.
Refer to market notice: 112063
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1120 hrs on 8 December 2023.
This is an AEMO autogenerated Market Notice.
[EventId:202312081015_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 December 2023 10:15
Issued by Australian Energy Market Operator Ltd at 1015 hrs on 8 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1015 hrs on 8 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region NSW1 Wednesday, 6 December 2023
NON-CONFORMANCE NSW1 Region Wednesday, 6 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: SUNTPSF1
Duration: 06/12/2023 07:30 to 06/12/2023 08:45
Amount: 51 MW
Constraint: NC-N_SUNTPSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 5 December 2023
NON-CONFORMANCE NSW1 Region Tuesday, 5 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: NEWENSF1
Duration: 05/12/2023 12:25 to 05/12/2023 12:45
Amount: 25 MW
Constraint: NC-N_NEWENSF1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202312041700_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 04 December 2023 17:00
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 4 December 2023
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 December 2023.
Refer to market notice: 112001
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1700 hrs on 4 December 2023.
This is an AEMO autogenerated Market Notice.
[EventId:202312041535_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 04 December 2023 15:35
Issued by Australian Energy Market Operator Ltd at 1535 hrs on 4 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1535 hrs on 4 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.