NON-CONFORMANCE Region NSW1 Thursday, 18 January 2024
NON-CONFORMANCE NSW1 Region Thursday, 18 January 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: DPNTBG1, DPNTBL1
Aggregate Dispatch Group: DPNTBESS_ADG1
Duration: 18/01/2024 14:50 to 18/01/2024 15:20
Amount: 19 MW
Constraint: NC-N_DPNTBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202401181400_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 18 January 2024 14:00
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 18 January 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 18 January 2024.
Refer to market notice: 113406
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1400 hrs on 18 January 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202401181200_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 18 January 2024 12:00
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 18 January 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 18 January 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1200 hrs on 18 January 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202401181100_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 18 January 2024 11:00
Issued by Australian Energy Market Operator Ltd at 1100 hrs on 18 January 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 18 January 2024.
Refer to market notice: 113401
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1100 hrs on 18 January 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202401180935_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 18 January 2024 09:35
Issued by Australian Energy Market Operator Ltd at 0935 hrs on 18 January 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 18 January 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0935 hrs on 18 January 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Thursday, 18 January 2024
NON-CONFORMANCE QLD1 Region Thursday, 18 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 18/01/2024 08:45 to 18/01/2024 09:25
Amount: -41 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202401171940_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 17 January 2024 19:40
Issued by Australian Energy Market Operator Ltd at 1940 hrs on 17 January 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 17 January 2024.
Refer to market notice: 113382
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1940 hrs on 17 January 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202401171905_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 17 January 2024 19:05
Issued by Australian Energy Market Operator Ltd at 1905 hrs on 17 January 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 17 January 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1905 hrs on 17 January 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region NSW1 Wednesday, 17 January 2024
NON-CONFORMANCE NSW1 Region Wednesday, 17 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW04
Duration: 17/01/2024 12:00 to 17/01/2024 12:15
Amount: 21 MW
Constraint: NC-N_BW04
Auto-generated on behalf of Manager NEM Real Time Operations