Filter by category
Filter by Date
[EventId:202412131520_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 December 2024 15:20
Issued by Australian Energy Market Operator Ltd at 1520 hrs on 13 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1520 hrs on 13 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202412131500_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 December 2024 15:00
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 13 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 December 2024.
Refer to market notice: 121844
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1500 hrs on 13 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412131330_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 December 2024 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 13 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1330 hrs on 13 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121820 has been updated at 1200 hrs 13/12/2024 to the following:
From 1600 hrs to 2030 hrs 17/12/2024.
The forecast capacity reserve requirement is 1044 MW.
The minimum capacity reserve available is 84 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 16/12/2024
The Forecast LOR2 condition in the VIC region advised in AEMO Electricity Market Notice No. 121821 is cancelled at 1200 hrs 13/12/2024.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121819 is cancelled at 1200 hrs 13/12/2024.
AEMO Operations
[EventId:202412131230_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 December 2024 12:30
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 13 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 December 2024.
Refer to market notice: 121829
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1230 hrs on 13 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412131105_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 December 2024 11:05
Issued by Australian Energy Market Operator Ltd at 1105 hrs on 13 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1105 hrs on 13 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region VIC1 Friday, 13 December 2024
NON-CONFORMANCE VIC1 Region Friday, 13 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BANN1
Duration: 13/12/2024 07:35 to 13/12/2024 08:00
Amount: 71 MW
Constraint: NC-V_BANN1
Auto-generated on behalf of Manager NEM Real Time Operations