120825RESERVE NOTICE22/11/2024 03:58:10 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120756 has been updated at 1400 hrs 22/11/2024 to the following:

1. From 1700 hrs to 1800 hrs 27/11/2024.
The forecast capacity reserve requirement is 1005 MW.
The minimum capacity reserve available is 613 MW.

2. From 1830 hrs to 2000 hrs 27/11/2024.
The forecast capacity reserve requirement is 1005 MW.
The minimum capacity reserve available is 525 MW.


AEMO Operations
     
120824RESERVE NOTICE22/11/2024 03:40:14 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 25/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120755 is cancelled at 1400 hrs 22/11/2024.

AEMO Operations
     
120823RESERVE NOTICE22/11/2024 03:41:30 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120757 is cancelled at 1400 hrs 22/11/2024.

AEMO Operations
     
120822RESERVE NOTICE22/11/2024 03:42:27 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120754 has been updated at 1400 hrs 22/11/2024 to the following:

1. From 1100 hrs to 1400 hrs 27/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.

2. From 1500 hrs to 1600 hrs 27/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.

3. From 1930 hrs to 2030 hrs 27/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 706 MW.


AEMO Operations
     
120821RESERVE NOTICE22/11/2024 03:43:23 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120753 has been updated at 1400 hrs 22/11/2024 to the following:

From 1300 hrs to 2359 hrs 26/11/2024.
The forecast capacity reserve requirement is 1555 MW.
The minimum capacity reserve available is 825 MW.


AEMO Operations
     
120820RESERVE NOTICE22/11/2024 03:44:25 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120751 has been updated at 1400 hrs 22/11/2024 to the following:

From 1600 hrs to 2100 hrs 25/11/2024.
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 828 MW.


AEMO Operations
     
120819RESERVE NOTICE22/11/2024 03:45:32 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120815 has been updated at 1400 hrs 22/11/2024 to the following:

From 1800 hrs to 1830 hrs 27/11/2024.
The forecast capacity reserve requirement is 525 MW.
The minimum capacity reserve available is 478 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120818RESERVE NOTICE22/11/2024 03:47:04 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120814 has been updated at 1400 hrs 22/11/2024 to the following:

1. From 1400 hrs to 1500 hrs 27/11/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 496 MW.

2. From 1600 hrs to 1930 hrs 27/11/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 341 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120815RESERVE NOTICE22/11/2024 02:11:58 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120810 has been updated at 1300 hrs 22/11/2024 to the following:

From 1700 hrs to 1930 hrs 27/11/2024.
The forecast capacity reserve requirement is 525 MW.
The minimum capacity reserve available is 32 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     