Filter by category
Filter by Date
Update - Non-credible contingency event - TAS region - 19/09/2024
Update - Non-credible contingency event - TAS region - 19/09/2024
At 1340 hrs the Gordon - Chapel St No1 and No 2 220 kV lines tripped.
AEMO did not instruct load shedding.
AEMO has advised of approximately 112 MW disconnection of bulk electrical load,
disconnection of generation at Studland Bay Wind generator (71 MW) and 23 MW generation reduction at Gordon Power station.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - TAS region - 19/09/2024
Non-credible contingency event - TAS region - 19/09/2024
At 1340 hrs the Gordon - Chapel St No1 and No 2 220 kV lines tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Wednesday, 18 September 2024
NON-CONFORMANCE SA1 Region Wednesday, 18 September 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 18/09/2024 11:20 to 18/09/2024 12:50
Amount: 21 MW
Constraint: NC-S_TB2HYB_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Tuesday, 17 September 2024
NON-CONFORMANCE SA1 Region Tuesday, 17 September 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MANNSF2
Duration: 17/09/2024 14:10 to 17/09/2024 15:00
Amount: 23 MW
Constraint: NC-S_MANNSF2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 10 September 2024
NON-CONFORMANCE QLD1 Region Tuesday, 10 September 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 10/09/2024 03:50 to 10/09/2024 04:10
Amount: 39 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 9 September 2024
NON-CONFORMANCE QLD1 Region Monday, 9 September 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 09/09/2024 17:25 to 09/09/2024 17:40
Amount: -32 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 9 September 2024
NON-CONFORMANCE QLD1 Region Monday, 9 September 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 09/09/2024 12:35 to 09/09/2024 13:05
Amount: 29 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Non-credible contingency event - VIC region - 06/09/2024
Update - Non-credible contingency event - VIC region - 06/09/2024
Refer AEMO Electricity Market Notice 118166
At 2005 hrs the Loy Yang PS No. 4 500 kV bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 6 September 2024
NON-CONFORMANCE QLD1 Region Friday, 6 September 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: WDBESSG1, WDBESSL1
Aggregate Dispatch Group: WDBESS_ADG1
Duration: 06/09/2024 13:45 to 06/09/2024 14:30
Amount: 101 MW
Constraint: NC-Q_WDBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations