Filter by category
Filter by Date
Inter-regional transfer limit variation - [outage element] - NSW region - 23/12/2023
Inter-regional transfer limit variation - [outage element] - NSW region - 23/12/2023
A planned outage of KEMPS CREEK No 2 525/345/34 kV Transformer in the NSW region was scheduled from 0600 hrs 23/12/2023 to 1200 hrs 23/12/2023.
The outage has been cancelled.
The following constraint set(s) invoked at 0600 hrs 23/12/2023
N-KC_TX
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q_MNSP1
NSW1-QLD1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Palmerston - Hadspen 2 220kV line - TAS region - 22/12/2023
Inter-regional transfer limit variation - Palmerston - Hadspen 2 220kV line - TAS region - 22/12/2023
At 1300 hrs 22/12/2023 there was a short notice outage of Palmerston - Hadspen 2 220kV line.
Constraint set(s) invoked: T-HAPM_220
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V - MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112483 is cancelled at 1100 hrs 18/12/2023.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112471 has been updated at 0500 hrs 18/12/2023 to the following:
From 1230 hrs 19/12/2023 to 1600 hrs 19/12/2023.
The forecast capacity reserve requirement is 1071 MW.
The minimum capacity reserve available is 42 MW.
AEMO is seeking a market response.
AEMO estimates that the latest time at which permission can be given for a planned outage to proceed is 0530 hrs on 19/12/2023.
Manager NEM RTO
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112427 has been updated at 1515 hrs 17/12/2023 to the following:
From 1230 hrs 19/12/2023 to 1600 hrs 19/12/2023.
The forecast capacity reserve requirement is 1346 MW.
The minimum capacity reserve available is 205 MW.
AEMO is seeking a market response.
AEMO estimates that the latest time at which permission can be given for a planned outage to proceed is 0530 hrs on 19/12/2023.
Manager NEM RTO
Inter-regional transfer limit variation: Hazelwood - South Morang No 1 500 kV Line (VIC) - Voltage Control
The Hazelwood - South Morang No 1 500 kV Line has been de-energised to manage voltages in the Victoria region.
The following constraint set was invoked at 0600 hrs 17/12/2023
V-HWSM
The constraint set contains equations with the following interconnectors on the LHS.
T-V-MNSP
V-S-MNSP1
V-SA
VIC1-NSW1
Refer to AEMO Network Outage Scheduler (NOS) for return to service details
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Sydney West - Vineyard No 29 330kV line - NSW region - 17/12/2023
Inter-regional transfer limit variation - Sydney West - Vineyard No 29 330kV line - NSW region - 17/12/2023
At 0545 hrs 17/12/2023 there was a short notice outage of Sydney West - Vineyard No 29 330kV line.
Constraint set(s) invoked: N-SWVY_29
The following constraint set(s) invoked at 0545 hrs 17/12/2023
N-SWVY_29
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112392 has been updated at 1530 hrs 16/12/2023 to the following:
From 1330 hrs to 1600 hrs 19/12/2023.
The forecast capacity reserve requirement is 685 MW.
The minimum capacity reserve available is 128 MW.
AEMO is seeking a market response.
AEMO estimates that the latest time at which permission can be given for a planned outage to proceed is 0530 hrs on 19/12/2023.
Manager NEM RTO
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112390 has been updated at 1600 hrs 15/12/2023 to the following:
From 1430 hrs to 1600 hrs 19/12/2023.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 171 MW.
AEMO is seeking a market response.
AEMO estimates that the latest time at which permission can be given for a planned outage to proceed is 0530 hrs on 19/12/2023.
AEMO Operations