Filter by category
Filter by Date
[EventId:202408051645_confirmed] Prices for interval 05-Aug-2024 16:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 16:45.
In accordance with Market Notice 117550 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408051635_confirmed] Prices for interval 05-Aug-2024 16:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 16:35.
In accordance with Market Notice 117548 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Cancellation of Actual (LOR1) condition in the SA region - 30/07/2024
Cancellation of Actual (LOR1) condition in the SA region - 30/07/2024
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No. 117509 is cancelled at 2040 hrs 30/07/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 30/07/2024
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 30/07/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2000 hrs.
The Actual LOR1 condition is forecast to exist until 2030 hrs
The capacity reserve requirement is 450 MW
The minimum capacity reserve available is 404 MW
Manager NEM Real Time Operations
Increase to QNI limit to next hold point of 1400 MW Qld to NSW
Refer to market notices 117060.
AEMO, TransGrid, Powerlink have reviewed the test results following the QNI minor testing on 19th June 2024. The next hold point can now be released.
The hold point of 1400 MW from Qld to NSW will be implemented as of 1000 hrs 31st July 2024.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
Network Augmentation Commissioned - VIC Region - 30/07/2024
Network Augmentation Commissioned - VIC Region - 30/07/2024
Cressy Terminal Station has been cut into the existing Moorabool - Mortlake No.2 500 kV line to form the following circuits:
Cressy - Mortlake No.2 500 kV line
Cressy - Moorabool No.2 500 kV line
Manager NEM Real Time Operations
Network Augmentation Commissioned - VIC Region - 18/07/2024
Network Augmentation Commissioned - VIC Region - 18/07/2024
At 2044 hrs 18,07/2024, Cressy Terminal Station has been cut into the existing Moorabool - Haunted Gully No.1 500 kV line to form the following circuits:
Cressy - Haunted Gully No 1 500 kV line
Cressy - Moorabool No 1 500 kV line
Manager NEM Real Time Operations
Load Shedding Direction in the NSW Region
Load Shedding Direction in the NSW Region
AEMO has directed load shedding commencing at 1817 hrs 08/07/2024
in the NSW region
to maintain power system security.
The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 03/07/2024
Cancellation of Actual (LOR1) condition in the NSW region - 03/07/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117284 is cancelled at 2010 hrs 03/07/2024.
Manager NEM Real Time Operations