Filter by category
Filter by Date
Inter-regional transfer limit variation - Pelican Point Circuit Breaker 8093 - SA region - 26/12/2023
Inter-regional transfer limit variation - Pelican Point Circuit Breaker 8093 - SA region - 26/12/2023
At 1832 hrs 26/12/2023 there was a short notice outage of Pelican Point Circuit Breaker 8093.
The following constraint set(s) invoked at 1855 hrs 26/12/2023
S-PPT_CB6727
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation: Hazelwood - South Morang No 1 500 kV Line (VIC) - Voltage Control
The Hazelwood - South Morang No 1 500 kV Line has been de-energised to manage voltages in the Victoria region.
The following constraint set was invoked at 0735 hrs 26/12/2023
V-HWSM
The constraint set contains equations with the following interconnectors on the LHS.
T-V-MNSP
V-S-MNSP1
V-SA
VIC1-NSW1
Refer to AEMO Network Outage Scheduler (NOS) for return to service details
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Greenbank - Mudgeeraba 835 275 kV line - QLD region - 25/12/2023
Inter-regional transfer limit variation - Greenbank - Mudgeeraba 835 275 kV line - QLD region - 25/12/2023
At 2102 hrs 25/12/2023 there was an unplanned outage of Greenbank - Mudgeeraba 835 275 kV line
Constraint set(s) invoked: Q-GBMU_835_836 from 2105 hrs
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q_MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Greenbank - Molendinar 8824 275 kV line - QLD region - 25/12/2023
Inter-regional transfer limit variation - Greenbank - Molendinar 8824 275 kV line - QLD region - 25/12/2023
At 2057 hrs 25/12/2023 there was an unplanned outage of Greenbank - Molendinar 8824 275 kV line
The outage has been returned to service at 2125 hrs 25/12/2023
Constraint set(s) invoked: Q-GBMO_8824_8825 from 2105 hrs to 2125 hrs
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q_MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the Qld Region on 29/12/2023
The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No.112596 is cancelled at 1430 hrs 23/12/2023.
[No LOR condition is currently forecast in the STPASA period.]
Manager NEM RTO
Inter-regional transfer limit variation - Palmerston - Hadspen 220 kV Line - TAS region - 23/12/2023
Inter-regional transfer limit variation - Palmerston - Hadspen 220 kV Line - TAS region - 23/12/2023
A planned outage of Palmerston - Hadspen 220 kV Line in the TAS region was scheduled from 1000 hrs 23/12/2023 to 1500 hrs 23/12/2023.
The outage has been completed and returned to service at 1045 hrs 23/12/2023
Constraint set(s) invoked:
T-HAPM_220
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V- MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - [outage element] - NSW region - 23/12/2023
Inter-regional transfer limit variation - [outage element] - NSW region - 23/12/2023
A planned outage of KEMPS CREEK No 2 525/345/34 kV Transformer in the NSW region was scheduled from 0600 hrs 23/12/2023 to 1200 hrs 23/12/2023.
The outage has been cancelled.
The following constraint set(s) invoked at 0600 hrs 23/12/2023
N-KC_TX
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q_MNSP1
NSW1-QLD1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1930 hrs 29/12/2023.
The forecast capacity reserve requirement is 1057 MW.
The minimum capacity reserve available is 1049 MW.
AEMO Operations
Inter-regional transfer limit variation - Palmerston - Hadspen 2 220kV line - TAS region - 22/12/2023
Inter-regional transfer limit variation - Palmerston - Hadspen 2 220kV line - TAS region - 22/12/2023
At 1300 hrs 22/12/2023 there was a short notice outage of Palmerston - Hadspen 2 220kV line.
Constraint set(s) invoked: T-HAPM_220
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V - MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations