Filter by category
Filter by Date
[EventId:202502041315_confirmed] Prices for interval 04-Feb-2025 13:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 4 February 2025
PRICES ARE NOW CONFIRMED for trading interval 04-Feb-2025 13:15.
In accordance with Market Notice 124071 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1700 hrs to 1830 hrs 07/02/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 576 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
NON-CONFORMANCE Region NSW1 Tuesday, 4 February 2025
NON-CONFORMANCE NSW1 Region Tuesday, 4 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 04/02/2025 12:05 to 04/02/2025 12:15
Amount: -57 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124061 is cancelled at 0800 hrs 04/02/2025.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1430 hrs to 1500 hrs 05/02/2025.
The forecast capacity reserve requirement is 976 MW.
The minimum capacity reserve available is 908 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 124042 is cancelled at 1715 hrs 03/02/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1900 hrs 03/02/2025 to 2000 hrs 03/02/2025.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 243 MW.
AEMO is seeking a market response.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 3 February 2025
NON-CONFORMANCE NSW1 Region Monday, 3 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 03/02/2025 10:35 to 03/02/2025 10:40
Amount: -132 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 124033 is cancelled at 1015 hrs 03/02/2025.
Manager NEM Real Time Operations