NON-CONFORMANCE Region QLD1 Friday, 17 January 2025
NON-CONFORMANCE QLD1 Region Friday, 17 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: KINGASF1
Duration: 17/01/2025 06:35 to 17/01/2025 06:55
Amount: 10 MW
Constraint: NC-Q_KINGASF1
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 16/01/2025
In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_BRIS_569B1432 from 1425 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 16 January 2025
NON-CONFORMANCE NSW1 Region Thursday, 16 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 16/01/2025 11:35 to 16/01/2025 11:40
Amount: -9 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 16 January 2025
NON-CONFORMANCE NSW1 Region Thursday, 16 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 16/01/2025 04:55 to 16/01/2025 05:00
Amount: -21 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 15/01/2025
Non-credible contingency event - NSW region - 15/01/2025
At 2019 hrs the Tomago - Taree (963) 132kV line and the Tomago - Brandy Hill (96C) 132kV line tripped.
AEMO did not instruct load shedding.
AEMO has been advised of disconnection of 80 MW of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 15/01/2025
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_BRIS_5699E75F from 1655 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
V-S-MNSP1
VIC1-NSW1
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123295 is cancelled at 1545 hrs 15/01/2025.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123289 has been updated at 1515 hrs to the following:
[1.] From 1630 hrs 15/01/2025 to 1800 hrs 15/01/2025.
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 1347 MW.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Murray - Lower Tumut 330 kV 66 line - NSW region - 15/01/2025
Inter-regional transfer limit variation - Murray - Lower Tumut 330 kV 66 line - NSW region - 15/01/2025
At 1400 hrs 15/01/2025 there was an unplanned outage of Murray - Lower Tumut 330 kV 66 line.
The following constraint set(s) invoked at 1415 hrs 15/01/2025
I-LTMS
This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,V-S-MNSP1,NSW1-QLD1,T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations