Non-credible contingency event - QLD region - 16/04/2025
Refer market notice: 126577
Non-credible contingency event - QLD region - 16/04/2025
At 2110 hrs the Greenbank - Molendinar 8825 275kV line tripped at the Molendinar end only.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
[EventId:202504141815_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 14 April 2025 18:15
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 14 April 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 April 2025.
Refer to market notice: 126550
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1815 hrs on 14 April 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202504141730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 14 April 2025 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 14 April 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 April 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 14 April 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202504111900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 11 April 2025 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 11 April 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 April 2025.
Refer to market notice: 126516
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 11 April 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202504111730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 11 April 2025 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 11 April 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 April 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 11 April 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202504101900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 10 April 2025 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 10 April 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 April 2025.
Refer to market notice: 126477
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 10 April 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202504101705_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 10 April 2025 17:05
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 10 April 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 April 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1705 hrs on 10 April 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202504091915_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 09 April 2025 19:15
Issued by Australian Energy Market Operator Ltd at 1915 hrs on 9 April 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 9 April 2025.
Refer to market notice: 126459
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.
The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1915 hrs on 9 April 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202504091900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 09 April 2025 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 9 April 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 9 April 2025.
Refer to market notice: 126448
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 9 April 2025.
This is an AEMO autogenerated Market Notice.