PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No.124021 is cancelled at 2345 hrs 02/02/2025.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 03/02/2025
The Forecast LOR2 condition in the VIC region advised in AEMO Electricity Market Notice No.124022 is cancelled at 2345 hrs 02/02/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 03/02/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:
[1.] From 1830 hrs 03/02/2025 to 1900 hrs 03/02/2025.
The forecast capacity reserve requirement is 823 MW.
The minimum capacity reserve available is 801 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1830 hrs 03/02/2025 to 1930 hrs 03/02/2025.
The forecast capacity reserve requirement is 404 MW.
The minimum capacity reserve available is 333 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/01/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 123750 is cancelled at 1120 hrs 27/01/2025.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/01/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1500 hrs 28/01/2025 to 1600 hrs 28/01/2025.
The forecast capacity reserve requirement is 1005 MW.
The minimum capacity reserve available is 972 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the Qld Region on 24/01/2025
The Forecast LOR2 condition in the Qld region advised in AEMO Electricity Market Notice No. 123636 is cancelled at 2340 hrs 23/01/2025
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 24/01/2025
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 123625 has been updated at 1700 hrs to the following:
[1.] From 1800 hrs 24/01/2025 to 1900 hrs 24/01/2025.
The forecast capacity reserve requirement is 813 MW.
The minimum capacity reserve available is 751 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 24/01/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1800 hrs 24/01/2025 to 1930 hrs 24/01/2025.
The forecast capacity reserve requirement is 816 MW.
The minimum capacity reserve available is 572 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations