Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 122451
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1630 hrs 02/01/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0700 hrs 03/01/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1530 hrs 03/01/2025 / further notice.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 122666
Direction is cancelled from: 0400 hrs 03/01/2025
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 122665
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1330 hrs 03/01/2025.
The direction update is issued at 1630 hrs 02/01/2025.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122633 has been updated at 1400 hrs 02/01/2025 to the following:
1. From 1400 hrs to 1530 hrs 06/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
2. From 1830 hrs to 2230 hrs 06/01/2025.
The forecast capacity reserve requirement is 1845 MW.
The minimum capacity reserve available is 1137 MW.
AEMO Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 122631
The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 03/01/2025.
The direction update is issued at 1600 hrs 01/01/2025.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 122630
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 03/01/2025.
The direction update is issued at 1600 hrs 01/01/2025.
Manager NEM Real Time Operations
Cancellation of Actual Minimum System Load (MSL) MSL1 event in the VIC Region on 01/01/2025.
Cancellation of Actual Minimum System Load (MSL) MSL1 event in the VIC Region on 01/01/2025.
Cancellation - Actual MSL1- VIC Region at 1400 hrs 01/01/2025.
Refer to Market Notice 122654 for MSL1.
Manager NEM Real Time Operations
Actual Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
Actual Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
Update to Market Notice 122653 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 01/01/2025.
Minimum regional demand is forecast to be 1398 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1535 MW
- MSL2 - 1035 MW
- MSL3 - 535 MW
The regional demand is below the MSL1 threshold. The actual MSL1 condition is forecast to exist until 1400 hrs.
Manager NEM Real Time Operations
Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
Update to Market Notice 122635
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 01/01/2025.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1560 MW
- MSL2 - 1060 MW
- MSL3 - 560 MW
The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
- From 1200 hrs 01/01/2025 to 1400 hrs 01/01/2025. Minimum regional demand is forecast to be 1415 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO is seeking a market response.
Manager NEM Real Time Operations