Filter by category
Filter by Date
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124191 has been updated to the following:
[1.] From 1600 hrs 06/02/2025 to 1730 hrs 06/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 887 MW.
[2.] From 1930 hrs 06/02/2025 to 2030 hrs 06/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1148 MW.
Manager NEM Real Time Operations
[EventId:202502051740_confirmed] Prices for interval 05-Feb-2025 17:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 5 February 2025
PRICES ARE NOW CONFIRMED for trading interval 05-Feb-2025 17:40.
In accordance with Market Notice 124198 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502051800_confirmed] Prices for interval 05-Feb-2025 18:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 5 February 2025
PRICES ARE NOW CONFIRMED for trading interval 05-Feb-2025 18:00.
In accordance with Market Notice 124203 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502051755_confirmed] Prices for interval 05-Feb-2025 17:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 5 February 2025
PRICES ARE NOW CONFIRMED for trading interval 05-Feb-2025 17:55.
In accordance with Market Notice 124202 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502051750_confirmed] Prices for interval 05-Feb-2025 17:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 5 February 2025
PRICES ARE NOW CONFIRMED for trading interval 05-Feb-2025 17:50.
In accordance with Market Notice 124201 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502051745_confirmed] Prices for interval 05-Feb-2025 17:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 5 February 2025
PRICES ARE NOW CONFIRMED for trading interval 05-Feb-2025 17:45.
In accordance with Market Notice 124199 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502051735_confirmed] Prices for interval 05-Feb-2025 17:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 5 February 2025
PRICES ARE NOW CONFIRMED for trading interval 05-Feb-2025 17:35.
In accordance with Market Notice 124196 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124157 has been updated to the following:
[1.] From 1730 hrs 06/02/2025 to 1900 hrs 06/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1182 MW.
Manager NEM Real Time Operations
CHG0100111 | Pre-Production | Pre-Prod eMDM February Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM February Maintenance Release
Change Start Date & Time: 11/02/2025 13:00:00 AEST
Change End Date & Time: 11/02/2025 17:00:00 AEST
Outage Start Date & Time: 11/02/2025 13:00:00 AEST
Outage End Date & Time: 11/02/2025 15:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .