Inter-regional transfer limit variation - MLTS-SMTS No1 500 kV line CB at SYTS - VIC region - 11/02/2025
Inter-regional transfer limit variation - MLTS-SMTS No1 500 kV line CB at SYTS - VIC region - 11/02/2025
At 1538 hrs 11/02/2025 there was an unplanned outage of MLTS-SMTS No1 500 kV line CB at SYTS .
The following constraint set(s) invoked at 1600 hrs 11/02/2025
V-SY_CB
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 11/02/2025
Referring to Market Notice 124466.
The power system security condition in the SA region, requiring AEMO to invoke the automated constraint set CA_SYDS_56BD5936 has ended at 1520 hrs.
Constraint set revoked: CA_SYDS_56BD5936
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 11/02/2025
In order to maintain the power system in a secure operating state in the SA region, AEMO has invoked automated constraint set CA_SYDS_56BD5936 from 1410 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
V-SA
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 11 February 2025
NON-CONFORMANCE NSW1 Region Tuesday, 11 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 11/02/2025 13:55 to 11/02/2025 14:00
Amount: -11 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 10 February 2025
NON-CONFORMANCE NSW1 Region Monday, 10 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GULLRWF2
Duration: 10/02/2025 11:15 to 10/02/2025 14:10
Amount: 13 MW
Constraint: NC-N_GULLRWF2
Auto-generated on behalf of Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA, VIC from 10 Feb 2025 to 14 Feb 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Adelaide West Terrace (39+ Deg C): 11th Feb, 12th Feb
Clare High School (39+ Deg C): 12th Feb
Mt Gambier Ap (39+ Deg C): 12th Feb
Port Augusta Ap (39+ Deg C): 11th Feb, 12th Feb
VIC
Mildura Ap (39+ Deg C): 12th Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025
Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025
At 0945 hrs 10/02/2025 there was an unplanned outage of Ingleburn - Wallerawang (77) 330 kV line.
The following constraint set(s) invoked at 0955 hrs 10/02/2025
N-X_AVMA_SSWW
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Saturday, 8 February 2025
NON-CONFORMANCE VIC1 Region Saturday, 8 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LYA2
Duration: 08/02/2025 07:55 to 08/02/2025 08:05
Amount: -39 MW
Constraint: NC-V_LYA2
Auto-generated on behalf of Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA, VIC from 07 Feb 2025 to 11 Feb 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Adelaide West Terrace (39+ Deg C): 11th Feb
Clare High School (39+ Deg C): 11th Feb
Mt Gambier Ap (39+ Deg C): 11th Feb
Port Augusta Ap (39+ Deg C): 10th Feb, 11th Feb
VIC
Mildura Ap (39+ Deg C): 7th Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning