Inter-regional transfer limit variation - Constraint invocation to manage Power System Security in NSW region - 25/01/2025
In order to maintain the power system in a secure operating state in the NSW region (Northern NSW) , AEMO has invoked constraint set #N-Q-MNSP1_E from 1720 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation -Bundy-Buronga (6F) 330 kV line - NSW region - 21/01/2025
Inter-regional transfer limit variation - - NSW region - 21/01/2025
At 1935 hrs 21/01/2025 there was a short notice outage of Bundy-Buronga (6F) 330 kV line
The following constraint set(s) invoked
I-BDBU_ONE
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,VIC1-NSW1,V-SA,T-V-MNSP1
The outage is scheduled to return to service at 1935 hrs 22/01/2025
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NEM Local Temperature Alerts for QLD, SA from 22 Jan 2025 to 26 Jan 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
QLD
Dalby Ap (37+ Deg C): 22nd Jan, 23rd Jan, 24th Jan
SA
Port Augusta Ap (39+ Deg C): 26th Jan
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Update - Pre dispatch demand forecast error - NEM regions
Update - Pre dispatch demand forecast error - NEM regions
Refer market notice: 123548
The issue relating to the Pre dispatch demand forecast error has been resolved.
Manager NEM Real Time Operations
Pre dispatch demand forecast error - NEM regions
Pre dispatch demand forecast error - NEM regions
AEMO is aware of an error in the Pre dispatch demand forecast for the NEM regions
AEMO is currently working to resolve the issue.
Dispatch results are not impacted.
Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 21/01/2025
Refer Market notice: 123507
Network Augmentation Commissioned - NSW Region - 21/01/2025
Commissioned: Bundey to Buronga 330 kV (6F) line.
Buronga No. 5 330 kV/330 kV phase shifting transformer
Manager NEM Real Time Operations
Update - Pre dispatch demand forecast error - NEM regions
Update - Pre dispatch demand forecast error - NEM regions
Refer market notice: 123513
The issue relating to the Pre dispatch demand forecast error has been resolved.
Manager NEM Real Time Operations
NEM Local Temperature Alerts for QLD, VIC from 21 Jan 2025 to 25 Jan 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
QLD
Dalby Ap (37+ Deg C): 22nd Jan, 23rd Jan, 24th Jan
Rockhampton Ap (39+ Deg C): 23rd Jan
VIC
Mildura Ap (39+ Deg C): 21st Jan
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Pre dispatch demand forecast error - NEM regions
Pre dispatch demand forecast error - NEM regions
AEMO is aware of an error in the Pre dispatch demand forecast for the NEM regions
AEMO is currently working to resolve the issue.
Dispatch results are not impacted.
Manager NEM Real Time Operations