Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 123201
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 15/01/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 14/01/2025, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 15/01/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
NEM Local Temperature Alerts for QLD, SA, VIC from 14 Jan 2025 to 18 Jan 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
QLD
Rockhampton Ap (39+ Deg C): 16th Jan
SA
Port Augusta Ap (39+ Deg C): 14th Jan
VIC
Mildura Ap (39+ Deg C): 14th Jan
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Cancellation of Actual (LOR1) condition in the NSW region - 13/01/2025
Cancellation of Actual (LOR1) condition in the NSW region - 13/01/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.123180 is cancelled at 2045 hrs 13/01/2025.
Manager NEM Real Time Operations
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
Refer market notice: 123171
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs.
The forecast capacity reserve requirement is 1365 MW.
The minimum capacity reserve available is 966 MW.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1700 hrs
The capacity reserve requirement is 1390 MW
The minimum capacity reserve available is 861 MW
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 12/01/2025
Cancellation - AEMO Intervention Event - SA region 12/01/2025
Refer to Market Notice 123112
The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 13/01/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123113
Direction is cancelled from: 1500 hrs 13/01/2025
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 14/01/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations