122440MARKET INTERVENTION23/12/2024 04:32:51 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122407

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 24/12/2024.

The direction update is issued at 1630 hrs 23/12/2024.

Manager NEM Real Time Operations
     
122436GENERAL NOTICE23/12/2024 10:28:53 AM

NEM Local Temperature Alerts for SA, VIC from 23 Dec 2024 to 27 Dec 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 25th Dec, 26th Dec

VIC
Ararat Prison (39+ Deg C): 26th Dec
Melbourne Olympic Park (39+ Deg C): 26th Dec
Mildura Ap (39+ Deg C): 26th Dec
Mortlake (39+ Deg C): 26th Dec

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
122435NON-CONFORMANCE23/12/2024 09:40:24 AM

NON-CONFORMANCE Region QLD1 Monday, 23 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 23 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 23/12/2024 09:25 to 23/12/2024 09:40
Amount: 36 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
122408MARKET INTERVENTION22/12/2024 04:01:37 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122373

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 24/12/2024.

The direction update is issued at 1600 hrs 22/12/2024.

Manager NEM Real Time Operations
     
122407MARKET INTERVENTION22/12/2024 04:00:18 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122372

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 24/12/2024.

The direction update is issued at 1600 hrs 22/12/2024.

Manager NEM Real Time Operations
     
122373MARKET INTERVENTION21/12/2024 03:53:54 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122312

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 23/12/2024.

The direction update is issued at 1600 hrs 21/12/2024.

Manager NEM Real Time Operations
     
122372MARKET INTERVENTION21/12/2024 03:52:37 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122311

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 23/12/2024.

The direction update is issued at 1600 hrs 21/12/2024.

Manager NEM Real Time Operations
     
122340MARKET INTERVENTION21/12/2024 03:54:16 AM

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer to Market Notice 122297

Direction is cancelled from: 0400 hrs 21/12/2024

Manager NEM Real Time Operations
     
122326MARKET SYSTEMS20/12/2024 04:16:29 PM

INC0139532 | Impact to Prudentials

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - ALERT

The service interruption relating to Prudentials & Settlements have now been resolved.
AEMO is working on the issue and will provide updates as more information becomes available.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm