Filter by category
Filter by Date
NEM Local Temperature Alerts for SA, VIC from 02 Jan 2025 to 06 Jan 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Clare High School (39+ Deg C): 4th Jan
Port Augusta Ap (39+ Deg C): 3rd Jan, 4th Jan, 5th Jan
VIC
Ararat Prison (39+ Deg C): 4th Jan
Mildura Ap (39+ Deg C): 4th Jan, 5th Jan
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Request for Generator Recall Information for the period 06/01/2025 for Region NSW
Refer to AEMO Electricity Market Notice no. 122697.
Please provide Generator Recall Information for the period 06/01/2025, by 1200 hrs on 03/01/2025 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 122631
The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 03/01/2025.
The direction update is issued at 1600 hrs 01/01/2025.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 122630
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 03/01/2025.
The direction update is issued at 1600 hrs 01/01/2025.
Manager NEM Real Time Operations
Cancellation of Actual Minimum System Load (MSL) MSL1 event in the VIC Region on 01/01/2025.
Cancellation of Actual Minimum System Load (MSL) MSL1 event in the VIC Region on 01/01/2025.
Cancellation - Actual MSL1- VIC Region at 1400 hrs 01/01/2025.
Refer to Market Notice 122654 for MSL1.
Manager NEM Real Time Operations
Actual Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
Actual Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
Update to Market Notice 122653 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 01/01/2025.
Minimum regional demand is forecast to be 1398 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1535 MW
- MSL2 - 1035 MW
- MSL3 - 535 MW
The regional demand is below the MSL1 threshold. The actual MSL1 condition is forecast to exist until 1400 hrs.
Manager NEM Real Time Operations
Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
Update to Market Notice 122635
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 01/01/2025.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1560 MW
- MSL2 - 1060 MW
- MSL3 - 560 MW
The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
- From 1200 hrs 01/01/2025 to 1400 hrs 01/01/2025. Minimum regional demand is forecast to be 1415 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO is seeking a market response.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 1 January 2025
NON-CONFORMANCE QLD1 Region Wednesday, 1 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 01/01/2025 00:00 to 01/01/2025 00:45
Amount: 40 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
Update to Market Notice 122588
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 01/01/2025.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1560 MW
- MSL2 - 1060 MW
- MSL3 - 560 MW
The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
- From 1100 hrs 01/01/2025 to 1400 hrs 01/01/2025. Minimum regional demand is forecast to be 1321 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO is seeking a market response.
Manager NEM Real Time Operations