Project Energy Connect (PEC-1) testing 31th January 2025 1100-1500 for flows from South Australia to Victoria direction up to 150 MW
Refer to market notice 123676
There is an opportunity for testing Project Energy Connect (PEC-1) for flows from South Australia to Victoria direction up to 150 MW on 31th January from 11:00hrs to 15:00hrs
This test includes switching of transmission lines and reactive plant in South Australia and in New South Wales.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
AEMO Operations
NEM Local Temperature Alerts for SA, TAS, VIC from 31 Jan 2025 to 04 Feb 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Adelaide West Terrace (39+ Deg C): 3rd Feb
Clare High School (39+ Deg C): 2nd Feb, 3rd Feb, 4th Feb
Mt Gambier Ap (39+ Deg C): 2nd Feb, 3rd Feb
Port Augusta Ap (39+ Deg C): 1st Feb, 2nd Feb, 3rd Feb, 4th Feb
TAS
Launceston Ti Tree Bend (33+ Deg C): 2nd Feb, 3rd Feb, 4th Feb
VIC
Latrobe Valley Ap (39+ Deg C): 2nd Feb
Mildura Ap (39+ Deg C): 1st Feb, 2nd Feb, 3rd Feb, 4th Feb
Mortlake (39+ Deg C): 3rd Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
[EventId:202501301835_review] Prices for interval 30-Jan-2025 18:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 30 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2025 18:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501301830_review] Prices for interval 30-Jan-2025 18:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 30 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2025 18:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501301825_review] Prices for interval 30-Jan-2025 18:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 30 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2025 18:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501301820_review] Prices for interval 30-Jan-2025 18:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 30 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2025 18:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501301815_review] Prices for interval 30-Jan-2025 18:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 30 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2025 18:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501301810_review] Prices for interval 30-Jan-2025 18:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1805 hrs on 30 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2025 18:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501301330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 30 January 2025 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 30 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 January 2025.
Refer to market notice: 123921
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 30 January 2025.
This is an AEMO autogenerated Market Notice.