123616NON-CONFORMANCE23/01/2025 06:05:16 AM

NON-CONFORMANCE Region QLD1 Thursday, 23 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 23 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 23/01/2025 05:50 to 23/01/2025 06:05
Amount: 38 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123593RESERVE NOTICE22/01/2025 06:14:27 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:


[1.] From 1830 hrs 22/01/2025 to 1900 hrs 22/01/2025.
The forecast capacity reserve requirement is 456 MW.
The minimum capacity reserve available is 343 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
123552GENERAL NOTICE22/01/2025 10:59:15 AM

NEM Local Temperature Alerts for QLD, SA from 22 Jan 2025 to 26 Jan 2025

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

QLD
Dalby Ap (37+ Deg C): 22nd Jan, 23rd Jan, 24th Jan

SA
Port Augusta Ap (39+ Deg C): 26th Jan

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
123551GENERAL NOTICE22/01/2025 10:28:28 AM

Update - Pre dispatch demand forecast error - NEM regions

AEMO ELECTRICITY MARKET NOTICE

Update - Pre dispatch demand forecast error - NEM regions

Refer market notice: 123548

The issue relating to the Pre dispatch demand forecast error has been resolved.

Manager NEM Real Time Operations
     
123550NON-CONFORMANCE22/01/2025 09:00:31 AM

NON-CONFORMANCE Region NSW1 Wednesday, 22 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 22 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 22/01/2025 08:50 to 22/01/2025 09:00
Amount: 18 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
123549RESERVE NOTICE22/01/2025 08:56:34 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 123546 is cancelled at 0800 hrs 22/01/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
123548GENERAL NOTICE22/01/2025 07:55:01 AM

Pre dispatch demand forecast error - NEM regions

AEMO ELECTRICITY MARKET NOTICE

Pre dispatch demand forecast error - NEM regions

AEMO is aware of an error in the Pre dispatch demand forecast for the NEM regions
AEMO is currently working to resolve the issue.
Dispatch results are not impacted.


Manager NEM Real Time Operations
     
123547NON-CONFORMANCE22/01/2025 06:45:21 AM

NON-CONFORMANCE Region QLD1 Wednesday, 22 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 22 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 22/01/2025 06:40 to 22/01/2025 06:45
Amount: 16 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123546RESERVE NOTICE22/01/2025 06:34:02 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1630 hrs 28/01/2025 to 1700 hrs 28/01/2025.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 570 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm