Filter by category
Filter by Date
[EventId:202501222200_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 January 2025 22:00
Issued by Australian Energy Market Operator Ltd at 2200 hrs on 22 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 January 2025.
Refer to market notice: 123585
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2200 hrs on 22 January 2025.
This is an AEMO autogenerated Market Notice.
Cancellation of Actual (LOR2) condition in the QLD region - 22/01/2025
Cancellation of Actual (LOR2) condition in the QLD region - 22/01/2025
The Actual LOR2 Condition in the QLD Region advised in AEMO Electricity Market Notice No.123594 is cancelled at 1945 hrs 22/01/2025.
Manager NEM Real Time Operations
[EventId:202501221930_NRM_NSW1_QLD1_stopped] NEGRES CONSTRAINT NRM_NSW1_QLD1 ceased operating from 22 January 2025 19:30
Issued by Australian Energy Market Operator Ltd at 1930 hrs on 22 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to QLD - 22 January 2025.
Refer to market notice: 123591
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to QLD directional interconnector.
The negative residue constraint NRM_NSW1_QLD1 ceased operating at 1930 hrs on 22 January 2025.
This is an AEMO autogenerated Market Notice.
Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 22/01/2025
Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 22/01/2025
An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1830 hrs.
The Actual LOR2 condition is forecast to exist until 1900 hrs.
The forecast capacity reserve requirement is 515 MW.
The minimum capacity reserve available is 395 MW.
AEMO is seeking an immediate market response.
An insufficient market response may require AEMO to implement an AEMO intervention event.
Manager NEM Real Time Operations
[EventId:202501221800_NRM_NSW1_QLD1_started] NEGRES CONSTRAINT NRM_NSW1_QLD1 started operating from 22 January 2025 18:00
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 22 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to QLD - 22 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to QLD directional interconnector.
The negative residue constraint set NRM_NSW1_QLD1 commenced operating from 1800 hrs on 22 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202501221645_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 January 2025 16:45
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 22 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1645 hrs on 22 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202501221530_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 January 2025 15:30
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 22 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 January 2025.
Refer to market notice: 123560
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1530 hrs on 22 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501221430_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 22 January 2025 14:30
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 22 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 22 January 2025.
Refer to market notice: 123571
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1430 hrs on 22 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501221405_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 22 January 2025 14:05
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 22 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 22 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1405 hrs on 22 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.